Abstract:Research purposes: The detailed introduction is given in this paper to the functions of the JGMZY 10 type multi-functional operation vehicle for tunnel. The vehicles functions are as follows: The folding arm crane can be used for installing the construction members and lifting the small parts in the limited space in tunnel and if the special fixture is used in stead of the hock, the arch can be lifted with mechanization. It provides the reference to the similar works.
Research conclusions:The JGMZY 10 type multi-functional operation vehicle for tunnel has the following features: (1) Its structure is simple, its design is reasonable and its operation is easy. (2) The mechanizations of the installations of the arch and waterproof plate can be achieved by using the JGMZY 10 type multi-functional operation vehicle for tunnel and it meets the mechanized construction requirement by the Ministry of Railways. (3) Its application in construction of the Fajishan Tunnel shows the working efficiency can be much enhanced by using it.
[1] 李艳.钢拱架安装台车的设计与研究[D].洛阳:河南科技大学,2011. Li yan. Design and Study for Steel Arch Erector Trolley [D]. Luoyang: Henan University of Science and Technology, 2011.
[2] 康宝生.一种新型隧道施工用拱架安装机[J]. 隧道建设,2011(31): 624-628. Kang Baosheng. A new Type of Steel Rib Installing Machine Used Intunneling [J]. Tunnel Construction, 2011(31): 624-628.
[3] 管振祥.电气化铁路防水板隧道防水板铺设技术[J].石家庄铁道学院学报,2003(1): 30-33. Guan Zhenxiang. Setting Technique of Waterproof Plate for Electrification Railway Tunnel [J]. Journal of Shijiazhuang Railway Institute, 2003(1): 30-33.
[4] 马克相. LDPE防水板在潭峪沟隧道应用[J].西部探矿工程,2002(6): 20-23. Ma Kexiang. The Applications of LDPE Waterproof Board in Tanyugou Tunnel [J]. West-china Exploration Engineering, 2002(6): 20-23.
[5] 林立军,周崇全.北川河桥钢管拱制作技术[J].魅力中国,2007(4): 122-123. Lin Lijun, Zhou Chongquan. Erection of the Steel Tube Arches of Installation Technology in Beichuan HeQiao [J]. Charming China, 2007(4): 122-123.
[6] 白恒恒.隧道地质超前预报方法的探讨和研究[J].铁道工程学报,2006(5): 12-16. Bai Hengheng. Research on Geological Forecast Method on Tunneling [J]. Journal of Railway Engineering Society,2006(5): 12-16.