Abstract:Research purposes:The Yellow River Bridge is a very important engineering of Shuozhou - Zhungeer Railway.The pier longitudinal displacement of large - span deck - type arch bridge is caused by the pier and arch - rib deformation.The abutment arrangement of simply supported T - beam has big effect on the loading bearing of the arch rib,therefore,it is necessary to arrange the abutment rationally to reduce the longitudinal displacement of the high pier and cut its adverse effects on the arch rib.
Research conclusions:(1) As the maximum relative longitudinal displacement of adjacent pier on the arch bridge occurs between the junction pier and G1 or G12 pier.(2) The movable abutment with large longitudinally displacement and expansion device should be used for the first beam at arch foot and the measures for prevention of span collapse should be taken.(3) As the pier top displacement of large - span arch bridge has big effect on the CWR track,the fastening with small resistance should be used for the CWR track on bridge to adapt the pier deformation.
周岳武;李凤芹;张亚丽. 准朔铁路黄河特大桥拱上简支 T 梁支座布置研究[J]. 铁道工程学报, 2012, 29(8): 49-54.
ZHOU Yue - wu,LI Feng - qin,ZHANG Ya - li. Research on Abutment Arrangement of Simply Supported T - beam of Yellow River Bridge of Zhungeer - Shuozhou Railway. 铁道工程学报, 2012, 29(8): 49-54.
Yang Kejian,Li Fengqin,Zhang Yali. Research on the Design of Large Span Deck Steel Tube Concrete Arch Bridge[J].Journal of Railway Engineering Society, 2008(12) : 67-71.
[6] 马庭林,徐勇,等.水柏铁路北盘江大桥设计[J]. 桥梁建设,2001(5) :25-32.
Ma Tinglin, Xu Yong,etc.Design of Beipanjiang Bridge on Shuicheng - Baiguo Line [J].Bridge Construction,2001(5) : 25-32.
Li Shengyong, Li Fengqin,etc.Analysis on Creep Effect of Concrete - filled Steel Tubular Arch Bridges [J].Journal of the China Railway Society,2011(3) : 100-107.
Zhao Yueyu,Liu Weichang,Feng Rui,etc. Simulation Calculation for Lifting and Erection Process of Arch Ribs of Long Span Concrete - filled Steel Tube Arch Bridges[J]. World Bridges,2006(2) : 38-40.