Jinbin Light Rail Reserved Station ( Binhai University Station ) in the Architectural Design |
SUN Ming,GAO Xing |
The Third Railway Survey and Design Institute Group Corporation,Tianjin 300251,China |
|
|
Abstract Research purposes: This paper sums up the related problems of the construction reserved engineering design in phase I of Jinbin subway,put forward feasible solution,and at the same time discusses the specific content of the reserved engineering in related project and the depth it need to reach. It can provide references for subsequent project.
Research conclusions: Reserved engineering in architectural design should be demonstrated sufficiently in the preliminary design stage,and the design depth must meet corresponding requirement. On this basis,we put forward requirements as definite land control etc. ,providing place and space for reserved engineering. Design details should consider the influence of the second construction on the line operation,reducing assignments near the rail,lowering interference in operation.
|
Received: 04 January 2011
|
|
|
|
|
[1] 施仲衡. 地下铁道设计与施工[M]. 陕西: 科学技术出版社, 1997.
Shi Zhongheng. Design and Construction of Metro[M].Shanxi: Technology Publishing House, 1997.
[2] GB 50157—2003,地铁设计规范[S].
GB 50157—2003,Code for Design of Metro[S].
[3] GB 50490—2009,城市轨道交通技术规范[S].
GB 50490—2009,Technical Code of Urban Tail Transit[S].
[4] 建标104—2008,城市轨道交通工程项目建设标准[S].
JB 104—2008,Built Standard of Urban Tail Transit Projects[S].
[5] GB 50091—2006,铁路车站及枢纽设计规范[S].
GB 50091—2006,Code for Design of Railway Station and Terminal[S].
[6] GB 50016—2006,建筑设计防火规范[S].
GB 50016—2006,Code of Design on Building Fire Protection and Prevention[S].
[7] 天津市市政工程设计研究院. 天津市地下铁道1 号线工程华山里站施工设计文件[R]. 天津: 天津市市政工程设计研究院, 2002.
Tianjin Municipal Engineering Design & Research Institute. Construction Design Document of Huashanli Station in Tianjin No. 1 Subway Project [R]. Tianjin: Tianjin Municipal Engineering Design & Research Institute, 2002.
[8] 天津市市政工程设计研究院. 天津市地下铁道1 号线工程复兴门站施工设计文件[R]. 天津: 天津市市政工程设计研究院, 2002.
Tianjin Municipal Engineering Design & Research Institute. Construction Design Document of Fuxingmen Station in Tianjin No. 1 Subway Project [R]. Tianjin:Tianjin Municipal Engineering Design & Research Institute, 2002.
[9] 铁道第三勘察设计院. 天津市区至滨海新区轨道交通工程一期工程中山门站施工设计文件[R]. 天津: 铁道第三勘察设计院, 2002.
The Third Railway Survey and Design Institute Group Corporation. Construction Design Document of Zhongshanmen Station in Track Transportation Project Phase I of Tianjin City to Binhai New Area [R]. Tianjin: The Third Railway Survey and Design Institute Group Corporation, 2002.
[10] 铁道第三勘察设计院. 津滨轻轨一期工程预留车站建设工程滨海大学站初步设计文件[R]. 天津: 铁道第三勘察设计院, 2009.
The Third Railway Survey and Design Institute Group Corporation. Preliminary Design Document of Binhai University Station in Reseved Station Project Phase I of Jinbin Railway [R]. Tianjin: The Third Railway Survey and Design Institute Group Corporation, 2009.
[11] 方昌福,胡京涛,陈罄超. 城市轨道交通高架线的设计研究[J]. 铁道工程学报, 2006( 5) : 91 - 96.
Fang Changfu,Hu Jingtao,Chen Qingchao. Research on Elevate Line Design of Urban Rail Transit[J].Jouranl of Railway Engineering Society,2006( 5) : 91 - 96.
|
|
|
|