PREVENTION AND TREATMENT OF ACCIDENT IN CONSTRUCTION OF BRIDGE AND CULVERT JACK-IN |
HAN Li-feng, XU Shu-zhen |
The First engineering Co. Ltd. of the Seventh Engineering Group Co. Ltd. of Chinese Railway |
|
|
Abstract The bridge prefabrication and culvert and overhead jack-in of railway are key points for construction of railway Overpass Bridge and culvert. The bridge and culvert jack-in is the most important thing for construction quality control of overpass bridge. Construction of bridge and culvert can be conducted by many methods, such as primary jack-in method, across jack-in method, split jack-in method and slot jack-in method. The commonly used one is primary jack-in method. The common failings for jack-in construction are as follows: overlarge deformation of rear back to cause stopping jack-in, settlement and crack of slide plate, crack of bunching tip of bridge and culvert and lateral displacement of track to influence train running. This paper describes the technical points for bridge and culvert jack-in construction in details and puts forward the technical measures for prevention and treatment of construction accident in combination with construction example. Practice shows the measures are feasible with getting good result.
|
Received: 16 September 2005
|
|
|
|
|
[1] |
铁道部第三工程局.铁路工程施工技术手册桥涵(中册)[M]. 北京:中国铁道出版社,1992.
|
[2] |
王承礼.铁路桥梁[M].北京:中国铁道出版社,1993.
|
[3] |
铁道部第四勘测设计院桥隧处.桥涵顶进设计与施[M].北京:中国铁道出版社,1983.
|
[4] |
TB10203-2002,铁路桥涵施工规范[S].
|
[6] |
TB10415-2003,铁路桥涵工程施工质量验收标准[S].
|
[7] |
TB10424-2003,铁路混凝土砌体施工质量验收标准[S].
|
[5] |
TB 10002.1-99,铁路桥涵设计基本规范[S].
|
[8] |
TB10210-2001/J118-2001,铁路棍凝土与砌体施工规范[[S].
|
|
|
|