Reinforcement Design of 160m Span Prestressed Concrete Continuous Rigid Frame Box Girder |
LI Xing-lin, LIAO Cheng-qiang |
China Railway Eryuan Engineering Group Co. Ltd, Chengdu,Sichuan 610031 ,China |
|
|
Abstract Research purposes:According to the disease of the continuous rigid frame box girder, the reasonable method is adopted to improve the rigidity and strength of the girder cross-section for the purpose of ensuring the safety of bridge structure.
Research conclusions: As the crack generated among end-span, side-span and mid-span(1/4~3/4L) of the web plate weaken the rigidity and strength of the cross-section, so the applied reinforcement method can improve the rigidity and strength of the cross-section with feasibility and money saving. Through making calculation and comparison, the amplitude variation of the internal force before and after cracking is small. Because of the loss of the vertical prestress, the shear force of the cross-section is close to or lower than the most unfavorable design value of shear force, resulting in large incipient fault of the bridge structure during operation , so it is necessary to improve the strength against shear force in time due to the loss of the vertical prestress. The inversion method is used to analyze the factors of the disease. With the sticking steel plate and thickening web plate of the girder, the loss of the rigidity and strength of the girder cross-section can be compensated
|
Received: 03 March 2008
|
|
|
|
|
[1] GB 50367-2006 ,混凝土结构结构设计规范[S].
[2] 刘来君,赵小星.桥梁加固设计与施工技术[M].北京: 人民交通出版社,2004.
[3] 谌润水,等公路旧桥加固技术与实例[M].北京:人民 交通出版社,2002.
[4]铁道部科学研究院佛山院.广州东南西环高速公路东圃 特大桥检测报告[R].佛山:铁道部科学研究院佛山院, 2007.
|
|
|
|