Abstract Research purposes: Combined with the upgrading of the Guangtong-Dali Railway, this paper analyzes the engineering measures and main technical standards for the upgrading project,including the comparison and selection of the upgrading schemes,ruling gradients,speed-raising upgrading, speed target value and the number of main tracks to provide the reference to the upgrading of exiting railways.
Research conclusions:(1)In the upgrading projects of existing railway,the existing railway is often unable to meet the demands of transportation due to its low standards, small transportation capacity and slow running speed. ( 2 ) Based on the idea of"capacity expansion by upgrading the existing line→capacity expansion and upgrading by building the second line→capacity expansion and upgrading by building the new double-track line",the systematic study was done on this project. Combined with the features of the topographical conditions,geological conditions and urban planning along the railway,an reconstruction plan suitable for the convenient transportation organization,coordination of the capacities between lines and stations and getting the good economic benefits and strong market competitive capacity was selected after making an economical and technical comparison.(3)This study results is also available for the other projects of upgrading of existing railway.
|
Received: 10 December 2012
|
|
|
|
|
[1]铁建函[2010]1408号,关于广通至大理铁路扩能改造工程初步设计的批复[S].
Railway Construction Letter[2010]No. 1408, About Reply Opinion to the Preliminary Design on Reconstruction of Guangtong-Dali Railway[S].
[2]中铁二院工程集团有限责任公司.改建铁路广通至大理 线扩能改造工程可研报告[R].成都:中铁二院工程集团 有限责任公司,2008.
China Railway Eryuan Engineering Group Co. Ltd. Feasibility Study on Reconstruction of Guangtong-Dali Railway[R].Chengdu : China Railway Eryuan Engineering Group Co. Ltd,2008.
[3]中铁二院工程集团有限责任公司.改建铁路广通至大理 线扩能改造工程预可研报告[R].成都:中铁二院工程集 团有限责任公司,2007.
China Railway Eryuan Engineering Group Co. Ltd. Pre- feasibility Study on Reconstruction of Guangtong-Dali Railway[R].Chengdu : China Railway Eryuan Engineering Group Co. Ltd,2007.
[4]郝瀛.铁路选线设计[M].北京:中国铁道出版社,1996. Hao Ying. Design of Railway Line[M].Beijing: China Railway Publishing House ,1996.
[5]王其昌.高速铁路土木工程[M].成都:西南交通大学出 版社,1999.
Wang Qichang. High-Speed Railway Civil Engineering [M].Chengdu: Southwest Jiantong University Press, 1999.
[6] GB 50090-2006,铁路线路设计规范[S].
GB 50090-2006 , Code For Design of Railway Line [ S ].
[7]詹振炎.铁路选线设计的现代理论和方法[M].北京:中 国铁道出版社,2001
Zhan Zhenyan. Modern Theory and Method on Design of Railway Line [ M ].Beijing: China Railway Publishing House,2001.
[8]朱颖.铁路设计理念的回顾和展望[J].铁道工程学报, 2007(1):1-5.
Zhu Ying. Review and Prospect of Railway Design Concept [ J ] . Journal of Railway Engineering Society, 2007(1):1-5.
[9]王玉泽.铁路线路设计回顾与思考[J].铁道工程学报, 2007(1):27-30.
Wang Yuze. Review and Reflection on Design of Railway Line[J].Journal of Railway Engineerding Society , 2007 (1) : 27-30.
[10]朱颖.铁路选线理念的创新与实践[J].铁道工程学报, 2009(6):1-5
Zhu Ying. Innovation and Practice on Railway Location Concept [ J ].Journal of Railway Engineerding Society , 2009(6):1-5.
|
|
|
|