Study on Settlement Regulations of Ground Surface and Bridge Pier Induced by Metro Station Construction with PBA Method |
REN Jian-xi, WANG Song, CHEN Jiang, SUN Jie-long, MENG Chang, ZHU Yuan-wei |
Xi'an University of Science and Technology, Xi'an, Shanxi 710054, China |
|
|
Abstract Research purposes: Based on an underground metro station project in Beijing with complicated conditions, the comparison of the settlement regulations of the ground surface and bridge pier obtained by conducting the FLAC simulation prediction with the actual measured data was made to know the settlement regulations of the ground surface and bridge pier induced by the metro station construction with PBA method for providing the technical support for the information construction of underground metro station.
Research conclusions: (1)The FLAC simulation showed that with the excavation of the pilot tunnel, the settlement of the ground surface gradually increased. The curve of the settlement groove gradually changed from double peaks to single peak due to the influence of the load of the upper bridge and the dead weight of the bridge on the surface soil with playing a major role in the surface settlement at the beginning of the excavation. The maximum surface settlement happened in the center position of pilot tunnel excavation. The maximum predicted value of the ground settlement was 24.75mm and the measured value was 25.51mm. The maximum predicted value of the bridge pier settlement was 5.11 mm and the measured value was 5.89mm. Both were basically the same. (2)The result showed that the PBA construction scheme for metro station and the in-site monitoring scheme were reasonable in design and the deformations of the ground surface and pier met the specification requirements. (3)This research result could provide the reference to construction and monitoring of the large-section metro station in the area with poor geological conditions.
|
Received: 09 June 2013
|
|
|
|
|
[1]丁烈云, 李炜明, 吴贤国, 等.武汉地铁施工对轻轨桥梁影响的数值与监测分析[J].铁道工程学报,2010(10):87-90.
Ding Lieyun, Li Weiming, Wu Xianguo, etc. Study on Construction Plan for Wuhan Metro in Key Area Under Complex Engineering Environment; Operational Analysis of Surrounding Light Rail Bridge[J]. Journal of Railway Engineering Society, 2010(10):87-90.
[2]王霆, 罗富荣, 刘维宁, 等.地铁车站洞桩法施工引起的地表沉降和邻近柔性接头管道变形研究[J].土木工程学报,2012(2):155-161.
Wang Ting, Luo Furong, Liu Weining, etc. Study of Surface Settlement and Flexible Joint Pipeline Deformation Induced by Metro Station Construction with PBA Method[J]. China Civil Engineering Journa1, 2012(2):155-161.
[3]杜彬, 谭忠盛, 王梦恕.地铁车站洞桩法施工对地层及邻近桩基的影响规律[J].北京交通大学学报, 2008(3):30-36.
Du Bin, Tan Zhongsheng, Wang Mengshu, Analysis of Stratum Deformation and Pile Foundation Response During Subway Station Built by Pile-Beam-Arch Construction Method[J]. Journal of Beijing Jiaotong University, 2008(3):30-36.
[4]关金龙, 萧潇.洞桩法施工车站地表沉降的有限差分法分析[J].山西建筑, 2007(5):274-275.
Guan Jinlong, Xiao Xiao. Finite-difference Analysis Appliance to Shallow Buried under Ground Excavated Tunnels with the Cavern-pile Method[J]. Shanxi Architecture, 2007(5):274-275.
[5]宋建, 樊赟赟, 霍延鹏.复杂条件下浅埋暗挖地铁车站施工地表沉降规律分析[J].现代隧道技术, 2012(6):88-92.
Song Jian, Fan Yunyun, Huo Yanpeng. Ground Surface Settlement Law of a Shallow-Depth Subway Station Under Complex Conditions[J]. Modern Tunnelling Technology, 2012(6):88-92.
[6]朱泽民.地铁暗挖车站洞桩法(PBA)施工技术[J].隧道建设, 2006(5):63-65.
Zhu Zemin. Pile-Beam-Arch (PBA) Construction Technology for Mined Metro Stations[J]. Tunnel Construction, 2006(5):63-65.
[7]袁扬, 刘维宁, 丁德云, 等.洞桩法施工地铁车站导洞开挖方案优化分析[J].地下空间与工程学报, 2011(7):1693-1696.
Yuan Yang, Liu Weining, Ding Deyun, etc. Analysis on Heading Excavation Optimization in Metro Station Constructed by Drift-PBA Method[J]. Chinese Journal of Underground Space and Engineering, 2011(7):1693-1696.
|
|
|
|