Research on Measurement Methods for Track Geometry with CPIV |
FU Heng-you1,LIU Cheng-long2 |
1.The Third Railway Survey and Design Institute Group Corporation, Tianjin 300142, China;2. Southwest Jiaotong University, Chengdu, Sichuan 610031,China |
|
|
Abstract Research purposes:The track geometry survey should be carried out before the fine adjustment of high — speed railway tracks. The current method is to use the CPIII resection at freely - occupied station for the track geometry measurement and compare the measured data with the designed parameters, and then the fine adjustment is made to make the various parameters of track regularity meeting the design requirements. Based on the features of track reference network ( CPIV) that its adjacent points have higher relative accuracy and its control points can be reserved forever for the operation maintenance, this paper presents a new method for the track geometry static inspection by using track gauge along with the force - centering device used for the occupied station and backsight on CPIV points. The trials on site with this method have been carried out in the practices.
Research conclusions:(1) The method of force - centering occupied station on CPIV for the static inspection of track geometry of ballastless slab has the merits of the short setting time and high efficiency. (2) By using the high precision between adjacent points, this method can ensure the high regularity of the track,and the experiments on site prove the measured results are correct and reliable, satisfying the code requirement. (3) The application of the CPIV network for track geometry can unify the control references for the track slab and track fine adjustment, getting better regularity indexes and being worthy of wide application. (4) The research achievement can be applied in the static inspection of track geometry on the stages of construction and operation maintenance,and has the reference value for the code compilation and improvement.
|
Received: 01 March 2013
|
|
|
|
|
[1] 魏晖,朱洪涛,万坚.绝对测量在无砟轨道的轨向控制中 的精度分析[J].铁道工程学报,2012(5) :1-5.
Wei Hul, Zhu Hongtao,Wan Jan. Analysis of Accuracy of Absolute Survey in Control of Horizontal Regularity of Ballastless Track[ J] ? Journal of Railway Engineering Society,2012(5):l-5.
[2] 刘成龙,杨友涛,徐小左.高速铁路CPIII交会网必要测量 精度的仿真计算[〗].西南交通大学学报,2008(6): 718 -723.
Liu Chenglong, Yang Youtao, Xu Xiaozuo. Simulated Determination of Accuracy Requirement for Control Points m Intersection Networks in High - speed Railway [ J ]. Journal of Southwest Jiaotong Uniwersity,2008(6) :718 -723.
[3] 徐万鹏.基于cpin网的板式无砟轨道精调系统[j].铁 道工程学报,2011(7):53-58
Xu Wanpeng. Fine - adjustment System for Slab Ballastles Track Based on CP m Control Net [ J ]. Journal of Railway Engineering Society,2011 (7) :53 - 58.
[4] 何永军,刘成龙,付恒友,等.高速铁路轨道基准网三维构 网及其平差方法研究[J].铁道科学与工程学报,2011 (13) :352-354.
He Yongjun,Liu Chenglong,Fu Hengyou,etc. Study on a New Method about the Three 一 dimensional Network Measurement and Adjustment Method for High – speed Railway Track Reference Network [ J ] ? Journal of Railway Society and Engineering,2011 (13) :352 -354.
[5] TB 10601-2009,高速铁路工程测量规范[S]
TB 10601~2009, Code for Engineering Survey of High Speed Railway [S].
[6] 陈海军,刘成龙,付恒友,等.高速铁路轨道基准网平面网 构网测量及严密平差方法研究[J].铁道科学与工程报,2011(8) :55-60.
Chen Haijun,Liu Chenglong, Fu Hengyou, etc. Research on the Network - constructed Measurement and Strict Adjustment Methods in the Plane Network of Track Reference Network of High - speed Railway [ J ]. Journal of Railway Society and Engineering, 2011 (8): 55 -60.
|
|
|
|