Abstract:Research purposes:Based on the Dashengguan Yangtze Rive Bridge in Nanjing, this paper analyzes the monitoring computation for the closure of the main arch of the steel truss arch bridge with three main steel trusses and studies the closure measures for the purposes of directing erection of the bridge, achieving the accurate closure in short time and providing the references to the similar works.
Research conclusions:The Dashengguan Yangtze Rive Bridge is a tri-steel truss and six-span continuous arch bridge with two main arch spans in the middle and two side spans on the both ends. The general scheme of using double cantilevers to erect the steel truss of the middle main pier, using single cantilever to erect the steel truss of the two side main piers and conducting closure in the middle of the two main arches was adopted for the closure of the main arch of this bridge. Through the analysis of the monitoring computation and the study on the closure measures for the main arch of the steel truss arch bridge with three main trusses, the series of closure measures were taken for accurate closure of the two main arches of the bridge, such as using long circle hole, circle hole, dowel, pushing and pulling device and temperature difference.
胡辉跃. 大胜关长江大桥主拱合龙措施及监控计算分析[J]. 铁道工程学报, 2010, 27(3): 49-51.
HU Hui-yue. Measures for Closure of Main Arch of Dashengguan Yangtze Rive Bridge and Analyses of Monitoring Computation. 铁道工程学报, 2010, 27(3): 49-51.