Abstract:Abstract : Research purposes : This paper focuses on difficulties in Dandong - Dalian railway signal engineering design, including integrated grounding at subgrade sections outside stations, remote video monitoring of switch gaps, balises setting at link stations to C3 sections and not - only - passenger stations,and dispatching design of Jinzhou station, analyzes the feasibilities of various programs,and proposes the ultimate solution. Research conclusions :( 1 ) The directly buried mode linking up grounding wire at subgrade sections outside stations could conform to requirements of ground resistance mostly. ( 2) Switch gap video monitoring system networking independently could make the remote monitoring real - time. (3) Balises setting mode of C2 and C3 at link stations to C3 sections should be compatible with each other. (4 ) Balises setting at not - only - passenger stations should satisfy requirements of transport. (5 ) Jinzhou station should have different centralized control mode of railway bureau or station,depending on requirements of transport. (6) The research result can provide reference for other similar railway project.
王嵩. 丹大线信号工程设计技术难点及解决方案研究[J]. 铁道工程学报, 2016, 33(10): 101-105.
WANG Song. Researchon the Difficulties and Solutions in Dandong - Dalian Railway Signal Engineering Design. Journal of Railway Engineering Society, 2016, 33(10): 101-105.