Research on Risk Management of Construction Project Near Passenger Dedicated Line |
CUI Li - hong |
The Engineering Management Center of Ministry of Railways,Beijing 100844,Chin |
|
|
Abstract Research purposes: The construction project near passenger dedicated line is easily affected by the contretemps to produce the influence on the safety of passenger dedicated line,with the features of the big and indeterminate risk. This paper studies the risk characteristic and the influence of the construction project near passenger dedicated line,and discusses the risk management of construction project near passenger dedicated line.
Research conclusions: The safety of passenger dedicated line must be put in the first place during the construction project near the passenger dedicated line,the policy of the " safety first,precaution crucial and comprehensive control" must be insisted on and the principle of the " consideration of the transport and construction together" should be followed to ensure the completion of transport and construction.
|
Received: 21 June 2011
|
|
|
|
|
[1] 铁办[2008]190 号,铁路营业线施工安全管理办法[S].
Railway Office [2008] No. 190,Railway Transit - line Construction Safety Management Measure[S].
[2] 铁建设[2010]162 号,铁路建设工程风险管理暂行办法[S].
Railway Construction [2010 ] No. 162, Railway Construction Engineering Risk Management Temporary Means[S].
[3] 铁运[2010]51 号,铁路营业线施工安全管理补充办法[S].
Railway Traffic [2010] No. 51,Railway Transit - line Construction safety Management Complementarity Measure[S].
[4] 崔丽红,等. 铁路工程建设项目风险管理问题的研究[J]. 中国铁路,2001( 11) : 23 -25.
Cui Lihong,etc. Research on Risk Management of Railway Engineering Construction Project[J]. China Railway,2001( 11) : 23 - 25.
[5] 崔丽红. 客运专线建设项目风险管理问题的研究[J]. 铁道工程学报,2011( 1) : 96 -98.
Cui Lihong. Research on Risk Management of Passenger - dedicated Line Construction Project[J]. Journal of Railway Engineering Society,2011( 1) : 96 - 98.
[6] 刘伊生,等. 中国铁路建设项目管理模式研究[J]. 铁道工程学报,1998( 1) : 65 -69.
Liu Yisheng,etc. Research on Management Mode of China Railway Construction Project[J]. Journal of Railway Engineering Society,1998( 1) : 65 - 69.
|
|
|
|