Design of Bridge Foundation in Karst Area and Its Construction Technology |
XIONG Liang1, YIN Feng2 |
1. China University of Geosciences, Wuhan, Hubei 430074, China; 2. Luotian County Construction Quality Supervision Station, Luotian, Hubei 438600, China |
|
|
Abstract Research purposes:Design and construction of bridge are the key points to the modern railway construction. It is difficult to design and construct the bridge in karst area because of the development of underlying karst under the bridge site, complex shapes of karst on the base and lots of karst carves. These maybe cause the stratum collapse, sudden change of rock surface and leakage of karst carve in course of construction of the bridge foundation. Based on the design and construction of one railway bridge in karst area, this paper sums up the experiences in design of the bridge foundation in karst area and its construction technologies and makes some proposal.
Research conclusions:The construction quality of bridge foundation in karst area can be guaranteed if the survey of karsts is done in details, a reasonable design is made, a scientific construction is conducted and strict inspection is made.
|
Received: 30 December 2008
|
|
|
|
|
[ 1 ] TB10027—2001, 铁路工程不良地质勘察规程[S].
[ 2 ] 万晓东. 在岩溶地质条件下桥梁桩基础应用[J]. 工程建设与管理, 2007(5): 147-149.
[ 3 ] 刘涛, 魏加志. 岩溶地基桥梁基础设计和施工[J]. 四川建筑, 2005, 25(2): 55 -56.
[ 4 ] 黄雅君. 岩溶地区桥梁设计及处理[J]. 路基工程, 2005(5): 103-105.
[ 5 ] 李浩勇. 宜万铁路岩溶地区桥梁桩基础处理的体会[J]. 铁道勘测与设计, 2007(2): 46-49.
[ 6 ] 陈如意. 岩溶发育地区钻孔灌注桩施工质量控制[J]. 路基工程, 2008(4): 94-95.
[ 7 ] 黎梓良. 岩溶地区桥梁桩基础施工[J]. 广东科技, 2008(3): 163-164.
[ 8 ] 陈凡, 徐天平, 陈久照. 基桩质量检测技术[M]. 北京: 中国建筑工业出版社, 2004.
|
|
|
|