Research on Structure Plan of the Combined Construction of Highway and Subway for Xujiapeng Station of Wuhan Metro |
OU Yang-Bong |
China Railway Siyuan Survey and Design Group Co. Ltd,Wuhan,Hubei 430063,China |
|
|
Abstract Research purposes:Wuhan Metro Line 7 Xujiapeng transfer subway station is combined construction to underground property development and crossing river highway tunnel,and it is a huge and complex structure. It has super deep foundation pit,is currently the most deep excavation of metro station. Because the distance from Yangtze River is 800m,it has the characteristics of rich groundwater, poor geological conditions,the complex surrounding environment,and the larger project risk. The key point of this research is to adopt which construction method,structure scheme and construction measures to ensure the smooth implementation of engineering safety and effectively.
Research conclusions:(1)The project adopts the top-down method construction and special construction process, which is the safe and effective engineering work to super large and deep foundation pit,and make the project smoothly and safely implement. (2)Double high pressure jet grouting pile is the advanced wall joints waterproof measures,so that the engineering of groundwater has been effectively controlled.(3)This engineering provides a successful example for similar super large and deep foundation pit waterproof curtain and even the wall joints waterproof design,and has a larger reference value for research,design,construction of a new subway station structure of combined construction of highway and subway.
|
Received: 03 April 2014
|
|
|
|
|
[1]魏重丽.武汉地铁徐家棚站设计方案研究[J].铁道工程学报,2012(6) :109-112.
Wei Chongli. Research on Plan for Xujiapeng Tranfer Station of Wuhan Metro [ J ]. Journal of Railway Engineering Society,2012(6) :109 -112.
[2]欧阳冬,沈婷,陈远洲,等.广深港高铁深圳福田站逆作法施工与设计[J].建筑结构,2012(3) :132 -136.
Ouyang Dong, Shen Ting, Chen Yuanzhou, etc. Topdown Construction and Design for Shenzhen Futian Subway Station of Guangzhou - Shenzhen - Hong Kong High - speed Rail [ J ]. Building Structure,2012 (3): 132-136.
[3]中铁第四勘察设计研究院集团有限公司.武汉地铁七号线徐家棚站施工方法研究报告[R].武汉:中铁第四勘察设计研究院集团有限公司,2013.
China Railway Siyuan Survey and Design Group Co. Ltd. Wuhan Metro Line Seven Station Xujiapeng Research Report on the Construction Method [ R ]. Wuhan: China Railway Siyuan Survey and Design Group Co. Ltd,2013.
[4]徐致均,赵锡宏.逆作法设计与施工[M].北京:机械工业出版社,2002.
Xu Zhijun,Zhao Xihong. Topdown Construction and Design [ M]. Beijing: China Machine Press,2002.
[5]王卫东,王建华.深基坑支护结构与主体结构相结合的设计、分析与实例[M].北京:中国建筑工业出版社, 2007.
Wang Weidong,Wang Jianhua. The Deep Foundation Pit Supporting Structure and Main Structure of the Combination of Design,Analysis and Application [ M ]. Beijing: China Architecture & Building Press,2007.
[6]中铁第四勘察设计研究院集团有限公司.武汉地铁七号线徐家棚站抗震专项研究报告[R].武汉:中铁第四勘察设计研究院集团有限公司,2013.
China Railway Siyuan Surv"y and D"sign Group Co. Ltd. Wuhan Metro Line Seven Xujiapeng Station Special Report of the Earthquake[ R]. Wuhan: China Railway Siyuan Survey and Design Group Co. Ltd, 2013.
[7]王文达,王旭生,于清.地下工程钢管混凝土柱-HC梁节点选型及力学性能研究[J].铁道建筑,2009(9) :66 - 70.
Wang Wenda,Wang Xusheng,Yu Qing. Research on Underground Engineering Concrete Filled Steel Tubular Column - RC Beam Node Selection and Mechanical Properties [ J ]. Railway Construction,2009 (9) : 66 - 70.
[8]中铁第四勘察设计研究院集团有限公司.武汉地铁七号线徐家棚站风险评估专项研究报告[R].武汉:中铁第四勘察设计研究院集团有限公司,2013.
China Railway Siyuan Survey and Design Group Co. Ltd. Risk of Wuhan Metro Line Seven Station Xujiapeng Assessment Special Report [ R ]. Wuhan: China Railway Siyuan Survey and Design Group Co. Ltd,2013.
|
|
|
|