Abstract The paper gives the introduction of the construction technique of a new-type track structure-Slab Non-ballast Track, which will be used on the bridge of Qinshen Special Railway Line for Passenger Transportation, and sheds light on a series of key construction techniques, mainly including: fabrication of the track slab, research and production of CA sand mortar, construction of concrete bearing and convex retaining wall, paving of track slab, pouring of CA sand mortar, construction of the filled cushion slab etc. All these will have the significant reference and application value for its employment to the bridge construction of the city overhead track and the express-railway.
|
Received: 16 January 2003
|
|
|
|
|
[1]吴成三.介绍国外新型轨下基础-板式轨道[J].铁道标准设计,1994,2.
[2]任静.板式轨道研究与设计初探[J].铁道标准设计.1996,Z1.
[3]翟婉明,等.高速铁路板式轨道动力特性研究[J].铁道学报,1996,6.
[4]王其昌,韩启孟.板式轨道设计与施工[M].
|
|
|
|