Abstract Analyze the condition of B27 bids works of Qinghuangdao-Shenyang dedicated passenger railway; conclude that the area of the yards to store the continuous welded rail is an important factor for welding train. Select the quantity of continuous welded rail deposited before laying in the yard as the optimized object, establish the model depending on the restricting relationship of the time in which the welding train work in the two laving track teams, analyze the parameter to reduce the condition of using the welding train. Then based on the technical flow of laying the continuous wedded rail, discuss the relationship of working procedure between the welding and others ,and indicate some important parameter in selecting the equipment. This paper is useful for selecting the equipment, drawing the construction management plan, adopting new technics.
|
Received: 05 May 2003
|
|
|
|
|
[1]陈庆仪.应用焊轨列车的可行性探讨[R].
[2]广钟岩.铁路无缝线路(第三版)[M].北京:中国铁道出版社,2001年4月.
[3]中铁五局.装备无缝线路长钢轨焊接列车的技术经济可行性研究报告[M].1999年7月.
[4]张未.铁路跨区间无缝线路[M].中国铁道出版社,2000/10.
[5]中国铁路工程总公司.新建铁路秦皇岛至沈阳客运专线B单元27、29标段投标书[R]. 1999年9月15日.
|
|
|
|