DESIGN OF PRESTRESSED ANCHOR BOLTS AND SIMULATING CALCULATION BY FINITE ELEMENT METHOD FOR ANCHOR BOLT-SPRAY SUPPORT IN BIG-SPAN TUNNEL WITH HARD ROCKS |
ZHOU Shu-ming |
Tunnel Survey & Design Institute, Zhong-tie (Groups) Co, Ltd |
|
|
Abstract The active mechanism, designing and construction method of the prestressed anchor bolts by the finite element method, simulating to calculate a skating rink which is 20.9 m width arc explored in this paper. It provides the designing and constructing experiences for the similar engineering projects in future.
|
Received: 05 April 2001
|
|
|
|
|
[1]铁道部隧道工程局勘测设计院.福州于山溜冰场施工设计[K].1997.
[2]中华人民共和国国家标准.锚杆喷射混凝上支护技术规范(GBJ86-85)[5].1990.
[3]卢肇钧,吴肖茗,张肇伸.锚杆技术及其应用[A].铁道部科学研究院铁道建筑研究所论文集[C].
[4]岩土工程手册编委会.岩土工程手册[M].中国建筑工业出版社,1984.
[5]程良奎,杨志银.喷射混凝土与土钉墙[M].中国建筑工业出版社,1984.
[6]国兆林.高强锚喷技术及现代隧道工程方法概论[M].铁道部隧道工程局,1999.
|
|
|
|