The Structural Design of Contact Channel of the First Domestic Metro Cross-river Interval |
SUN Xue-bing |
China Railway Siyuan Survey and Design Group Co. Ltd, Wuhan, Hubei 430063, China |
|
|
Abstract Research purposes: The contact channel of Wuhan Metro Line 2, is the first built in the sand layer under Yangtze River of domestic metro. With Pump room of 3# contact channel bears the load of elevating head about 56 m, so it has the characteristics of heavy loads and construction of high risk. There is no precedent for reference, and a reasonable structural design solution should be used to ensure the structural safety and construction safety.
Research conclusions: In this paper, research and analysis on 3# contact channel with pump room are made, with the following main conclusions: (1)Practice has proved that the use of the river bottom sand freezing method is safe and reliable. But it should be possible to optimize the effective volume of the pump, reduce the sump volume, reduce the risk of freezing construction. (2)The conventional rectangular cross-section sump design is difficult to satisfy dual requirements of the freezing construction and structure of the high-pressure shear. (3)The contact channel taking the structure of the wall of variable thickness design and sump using nearly oval cross-section design, made an unexpected result which not only overcomes the problem of high pressure shear, the new structure type but also greatly improves force structure, improves structural safety affluence. (4)Currently this kind of contact channel structure type can provide the reference for the similar tunnel design.
|
Received: 29 September 2013
|
|
|
|
|
[1] GB 50157-2003, 地铁设计规范 [s].
GB 50157-2003, The Specification of Metro Design [S].
[2] 姚云泉, 张磊, 张新刚, 等. 广州市轨道交通四号线联络通道设计与施工工艺 [J]. 安全与环境工程, 2012(5):140-143.
Yao Yunquan, Zhang Lei, Zhang Xingang, etc. Design and Construction Technology of the Connecting Passage of No.4 Rail Transit in Guangihou[J]. Safety and Environmental Engineering, 2012(5):140-143.
[3] 丁光莹, 章仁财, 罗良友. 大连路隧道江底联络通道冻结施工技术 [J].地下工程与隧道, 2003(3):30-34.
Ding Guangying, Zhang Rencai, Luo Liangyou. The Freezing Construction Technology of Connecting Passage in Underwater of Dalian Road Tunnel [J]. Underground Engineering and Tunnels, 2003(3):30-34.
[4] 中铁第四勘察设计院集团有限公司. 武汉市地铁二号线一期工程江汉路一积玉桥站区间施工图 [R]. 武汉: 中铁第四勘察设计院集团有限公司, 2011.
China Railway Siyuan Survey and Design Group Co.Ltd. The Working Drawing of Jiang Han Road to Ji Yu-qiao Interval of First-phase Project of Wuhan No.2 Subway Line [R]. Wuhan: China Railway Siyuan Survey and Design Group Co. Ltd, 2011.
[5] 杨太华. 越江隧道工程联络通道冻结法施工风险分析 [J). 地下空间与工程学报, 2010(6): 1201-1206
Yang Taihua. Risk Analysis of Freezing Method Applied to Adjacent Passage Construction of Cross-river Tunnel Project [J]. Chinese Journal of Underground Space and Engineering, 2010(6):1201-1206.
[6] 王灵敏, 王先锋. 冻结法施工越江隧道联络通道工程事故分析 [J]. 建筑施工, 2005(8):51-53.
Wang Lingznin, Wang Xianfeng. An Accident Analysis of Communication Passage for River-crossing Tunnel Engineering with Freezing Construction Method [J]. Building Construction, 2005(8):51-53.
[7] 王士民, 何川, 高云龙. 高水压条件下盾构隧道联络通道及集水井施工力学行为研究 [J]. 铁道学报, 2012(7):108-114.
Wang Shimin, He Chuan, Gao Yunlong. Construction Mechanics Behavior of Interconnecting Aisle and Sump Pit of Shield Tunnel under High Hydraulic Pressure [J]. Journal of the China Railway Society, 2012 (7):108-114.
[8] 任志坚, 佘才高. 南京地铁盾构隧道联络通道设计与施工 [J]. 都市快轨交通, 2005(5):50-53.
Ren Zhijian, She Caigao. The Design and Construction of Shield Tunnel in Nanjing Metro [J]. Urban Rapid Rail Transit, 2005(5):50-53.
[9] 王晖, 竺维彬, 李大勇. 富水砂层中联络通道施工工法及其控制措施 [J]. 铁道工程学报, 2010(9):82-87.
Wang Hui, Zhu Weibin, Li Dayong. Construction Method and Control Measure for Connecting Passage in Water-enriched Sand Bed [J]. Journal of Railway Engineering Society, 2010(9):82-87.
|
|
|
|