Abstract Research purposes: Construction of the cement emulsified-asphalt mortar filling layer of CRTSⅡ slab ballastless track requires high technology and this technology is applied in China for a short time. Establishing, improving and implementing the management system for the construction technology are essential to the construction quality control of the mortar filling layer.
Research conclusions: From the construction of the cement emulsified-asphalt mortar layer of the ballastless track of the Hangzhou-Ningbo Passenger Dedicated line,it was concluded the development organization would begin with strengthening the management to focus on the system building, personnel training, source control and process management to form a full set of the technical management system for the construction quality control of mortar filling layer.
|
Received: 20 November 2012
|
|
|
|
|
[1] 铁工管 [2009] 67号,关于客运专线板式无砟轨道水泥乳化沥青砂浆管理指导意见[S]. TGG [2009] No.67, Guidance on Cement Emulsified-asphalt Mortar Management of PDL Slab Track [S].
[2] 科技基 [2008] 74号,客运专线铁路CRTSII型板式无砟轨道水泥乳化沥青砂浆斩行技术条件[S] KJJ [2008] No.74, Provisional Technical Conditions for Cement Emulsified-asphalt Mortar of PDL Railway CRTSII Slab Track [S].
[3] TB 10754-2010 ,高速铁路轨道工程施工质量验收标准[S]. TB 10754-2010, Standard for Construction Quality Acceptance of High-speed Railway Track Engineering [S].