Analysis of Deep Excavation of Fuzhou Station North Plaza |
MENG Chang – jiang |
(China Railway Siyuan Survey and Design Group Co. Ltd, Wuhan,Hubei 430063,China) |
|
|
Abstract Research purposes : As for the existence of the deep silt layers at Fuzhou Station north plaza,according to the actual environment adjacent to the existing railway station at the south side and without important buildings around the other side,considering the requirements of the time limit for a project,this paper developed excavations supporting scheme using the row pile + vertical inclined brace at the south side and sloped ejector anchor + platform + cantilever pile around the other side. The design scheme and monitoring results of this project can be used for reference of similar projects.
Research conclusions :(1) In view of the larger excavations of soft soil area,according to the requirements of the lateral wall of the excavations with different control,we formulate the scheme of row pile of displacement control combined with vertical inclined supporting and sloping of stability control with cantilever pile,the reasonable conclusion was verified by the monitoring data which can be used for reference of similar projects. (2) In the process of excavations design,we should pay attention to the actual situation of the side wall of excavations,and use existing reinforcement measures to improve the geotechnical parameters reasonably,to save engineering investment and shorten the time limit. ( 3 ) During the construction,the overload of the excavations should be strictly controlled,the deformation quantity of the excavations should be in the allowable range,and the risk of excavations accidents should be reduced. (4) The research results can provide guidance for the design and construction of deep excavation in soft soil area.
|
Received: 23 July 2015
|
|
|
|
|
|
|