Research on Change Plan and Pushing on Strategy for Tbilisi Ring Railway Project |
TIAN Guang-wen |
Chongqing Survey,Design and Research Institute Co, Ltd of China Railway Eryuan Engineering Group Co. Ltd, Chongqing 400020,China |
|
|
Abstract Research purposes: The overseas project under EPC contract needs the big investment and faces the high project risk, but it still has the free space for avoiding the investment and project risks. In this paper, the research is done on the overall design,the specific engineering solutions,the change plan and the pushing on strategy of the Tbilisi ring railway project in order to achieve the goals of controlling project investment, getting the maximum economic benefits and realizing win - win.
Research conclusions : (1) The more attention should be paid to the technical characteristics of EPC project and the particularity of total price contract. The requirements of the owner and contract should be met with small cost. (2) The design scheme should broadly consider the interests and benefits of the project and the interests of all parties involved should be taken into account,especially the contractor. In addition,the technology,risk and investment control should be balanced. (3 ) The good strategy should be used to push on the change plan step by step and from easy area to difficult area on full consideration of the concerns of the owner and supervisor to persuade them to understand and accept the design scheme that is favorable for the all parties. (4) This research result can be as the reference to the similar works.
|
Received: 04 November 2012
|
|
|
|
|
[1] CHhII 32—01—95,1520 mm 轨距铁路[S].
CHhII 32~01~95,1520 mm Gauge Railways[S].
[2]韦忠信,管百海,马兰.工程总承包商的纵向一体化研究 [J].铁道工程学报,2008 (11):96-98.
Wei Zhongxin,Guan Baihai,Ma Lan. Research on the Vertical Integration of General Construction Contractor [J ].Journal of Railway Engineering Society ,2008 (11): 96-98.
[3]胡海勇,李永妮.浅谈海外EPC总承包项目的设计管理 [J].公路交通科技应用技术,2011 (2) :207 - 210.
Hu Haiyong, Li Yongni. Preliminary Discussion on the Design Management of Overseas EPC General Contract Project [ J]. Journal of Highway and Transportation Research and Development ,2011(2) :207 - 210.
[4]吴利利,殷宏.EPC海外土木工程项目设计代表工作初探 [J].科技情报开发与经济,2008(26) :225 -226.
Wu Lili, Yin Hong. Probe into the Design Representative engineer in EPC Oversea Civil Engineering Project [ J], Sci-Tech Information Development & Economy,2008 (26) ;225 - 226.
[5]殷继兴.海外铁路EPC项目的设计管理和优化对策[J]. 高速铁路技术,2012(2) :6-9.
Yin Jixing. Optimal Strategy and Design Management for China,s Overseas Railway EPC Project [ J ]. High Speed Railway Technology ,2012(2) :6 -9.
[6]卓建成.困难山区铁路工程布局设计研究[J].铁道工程 学报,2009(12) :5 -7.
Zhuo Jiancheng. Research on the Engineering Arrangement Design for Railways in Difficult Mountain Area [ J ].Journal of Railway Engineering Society,2009 (12):5-7.
[7]中铁二院工程集团有限责任公司.第比利斯绕城铁路站 前施工设计图[R].成都:中铁二院工程集团有限责任 公司,2012.
China Railway Eryuan Engineering Group Co. Ltd. Infrastructure Construction Design Drawings for Tbilisi Railway Bypass Project [R], Chengdu: China Railway Eryuan Engineering Group Co. Ltd,2012.
|
|
|
|