Research on the Key Technology of Construction of Moving Formwork for Double-width Parallel Box Girder |
WANG Jie, QIAN Youwei |
The Second Engineering Co. Ltd of China Tiesiju Civil Engineering Group, Suzhou, Jiangsu 215131, China |
|
|
Abstract Research purposes:The moving formwork cast-in-situ box girder construction technique has been applied to many projects at home and abroad. At present, it is mainly the single-width moving formwork. In the case of cast-in-situ box girder with double width and small spacing, ordinary conventional single-width moving formwork construction is limited by the beam width, in the construction of the second picture box girder, the formwork cannot be moved longitudinally, and the use scope is limited. Therefore, through the research on the construction technology of the 50 m double-width cast-in-place box girder of Lingkun super bridge of Wenzhou Railway Line S1, this paper aims to form a set of key construction technology of the double-width parallel cast-in-place box girder. Research conclusions:(1) The finite element calculation results of the key components of the double-width parallel box girder moving formwork are in good agreement with the measured data of the preloading test; (2) The concrete pouring sequence of the moving formwork of double-width parallel box girder is reasonable, and the layout of the pouring equipment, the concrete conveying mode and the longitudinal movement mode of the formwork meet the construction needs; (3) Innovative design of double-width parallel making box girder moving formwork structure, use of folding the inner and outer formwork and bottom formwork for many times, realize the parallel manufacturing of the near distance box girder double beam, and the formwork tail is equipped with transverse adjustment cylinder, which solves the problem of small radius curve passing through holes; (4) The research results can provide reference for the design and construction of other similar projects.
|
Received: 19 August 2021
|
|
|
|
|
[1] |
王新存.桥梁工程中连续箱梁移动模架施工技术应用研究[J].交通世界,2021(18):52-53.Wang Xincun. Research on Application of Continuous Box Girder Moving Formwork Construction Technology in Bridge Engineering[J]. TranspoWorld,2021(18):52-53.
|
[2] |
谢甲闰.桥梁工程中移动模架施工技术及安全控制[J].交通世界,2019(32):72-73.Xie Jiarun. Construction Technology and Safety Control of Moving Formwork in Bridge Engineering[J]. TranspoWorld, 2019(32):72-73.
|
[3] |
吴尚德.高速铁路桥梁移动模架结构计算及预拱度设置[J].铁道工程学报,2013(2):58-62.Wu Shangde. Calculation of Movable Die Carrier and Determination of Pre-camber of Bridge of High-speed Railway[J]. Journal of Railway Engineering Society, 2013(2):58-62.
|
[4] |
王龙奉.大型造桥机挠度曲线与主梁剖分式结构研究[D].西安:长安大学,2006.Wang Longfeng. Research on Deflection Curve and Main Beam Partition Structure of Large Bridge Builder[D]. Xi′an: Chang′an University, 2006.
|
[5] |
吕彭民,王斌华,刘兴车.大型造桥机工作状态数值模拟与试验[J].长安大学学报:自然科学版,2008(2):104-107.Lv Pengmin, Wang Binhua, Liu Xingche. Numerical Simulation and Test of Large Overhead Launching Gantry[J]. Journal of Chang′an University:Natural Science Edition, 2008(2):104-107.
|
|
|
|