Evaluation Model for Bidding Risk of BOT Project of Passenger Dedicated Line |
XU Ya - min,XIAO Chao - qian |
1. Jining College,Jining,Shandong 273155,China; 2. China Railway Eryuan Engineering Group Co. Ltd,Chengdu,Sichuan 610031 China |
|
|
Abstract Research purposes: With the shortage of construction funds and inadequate infrastructure being increasingly prominent in China,to speed up the construction of railways and other infrastructure with the commonly - used BOT mode in the world is inevitable of the development of the era. The bidding scheme quality is crucial to the success bidding. As the BOT project has the features of long construction period,large construction investment,needing complex technology,many changeable factors and big project risk,the bidder will take the big risk when drawing up the bidding scheme.
Research conclusions: Staring with the system theory,the decision - making evaluation index system is established for the bidding scheme for the BOT project of passenger dedicated line and the evaluation is made with grey situation decision - making model. In the railway BOT project,there are lots of factors to influence the project risks and it is difficult to determine the relations among the influence factors. Now the commonly - used evaluation methods include thecomprehensive fuzzy evaluation model,ANN model and so on. These methods have their own advantages,but also they have disadvantages. With these methods,the differences of the comprehensive optimization index values are not obvious of various schemes and the model results are affected by the objective factors. Especially,with these methods,the high risks of railway BOT project can not be considered. The result of the model presented in this paper can not be affected by the objective factors,so this model is more accurate and effective in revealing the differences of the comprehensive optimization index values of various bidding schemes. This model has universal property,so it can be available for BOT projects of the highway and power supply.
|
Received: 15 July 2011
|
|
|
|
|
[1] S. Q. Wang,L. K. Tiong. Case Study of GovernmentInitiatives for PRC 's BOT Power Plant Project[J].International Journal of Project Management,2000( 18) : 69 -78.
[2] Huber P J. Projection Pursuit ( with discussion) [J].The Annals of Statistics,2005( 2) : 435 - 475.
[3] C. K. Prahalad,GaryHame. The Core Competence of the Corporation[ J]. Harvard Business Review,2007( 3) : 79 -91.
[4] Paul R Milgrom,Robert J Weber. A Theory of Auctions and Competitive Bidding [J]. Econometrica,1982 ( 5) :25 - 30.
[5] Ji - FengDing,Gin - Shuh Liang. Using fuzzy MCDM to Select Partners of Strategic Alliances for Liner Shipping[J]. Information Sciences,2005( 7) : 197 - 225.
[6] Ching - Tong Lin,Ying - Te Chen. Bid Decision -making - a Fuzzy Linguistic Approach [ J ]. International Journal of Project Management,2004 ( 22) : 585 -593.
[7] Mosehi O,Hegazy T,Fazio P. DBID: Analogy - based DSS for Bidding in Construction [J]. Journal of Construction Engineering and Management,1993 ( 3 ) : 466 - 479.
[8] 杨宏伟,周晶,何建敏. 基于博弈论的交通 BOT 项目特许权期的决策模型[J]. 管理工程学报,2007( 2) : 158 -162.
Yang Hongwei,Zhou Jing,He Jianmin. Traffic BOT Project Concession Period of Decision - making Model Based on Game Theory [J]. Management Project Journal,2007( 2) : 158 - 162.
[9] 黎建强. 多风险因素的投标报价决策方法[J]. 运筹与管理,2002( 2) : 19.
LI Jianqiang. Methods for Bidding under Risk [J]. Operations Research and Management Science,2002 ( 2) : 19.
|
|
|
|