2009 Vol. 26, No. 5
Published: 2009-05-15
1
Analyses of the Causes for Wind Disaster in Strong Wind Area along Lanzhou-Xinjiang Railway and the Effect of Windbreak
GE Sheng—chang,JIANG Fu—qiang
Research purposes: This paper analyzes the causes for the wind disasters in 100一kilometer wind area along the Lanzhou—Xinjiang Railway and the front 100一kilometer wind area along the Nanjiang Railway,studies the changes of wind speed after the wind break with the different heights and different interval space,and evaluates the effect of windbreak based on the measurement of shielding effect of the windbreak.
Research conclusions: The strong wind in the strong wind area along Lanzhou—Xinjiang Railway mainly belongs to inland cold wind with the characteristics of high wind speed,long wind season,stable wind direction and quick winding due to the narrow tube effect,downhill wind and large convection current of atmosphere caused by the topography.The field measurement shows that the effect of windbreak is significant,namely the speed of the wind behind the 3 m hish windbreak iS much lower than that outside the windbreak and the shielding scope of windbreak exceeds 38m when wind speed is 20m/s,which effectively weakens the train overturning moment.However,it is necessary to do the further research on the effect of windbreak on reducing the wind disaster under different conditions and the conclusions offered in this paper can provide references to control sandstorm Mong railway in the future.
2009 Vol. 26 (5): 1-4 [
Abstract
] (
2539
)
HTML
(1 KB)
PDF
(270 KB) (
159
)
5
Subsidence Monitoring System and Subsidence Prediction for the Subgrade of Wuhan—Guangzhou Passenger Dedicated Line
WANG Guang—yong
Research purposes: Nowadays the study on the subgrade subsidence theory,especially on the subsidence mechanism is done not much.There is a big gap between the calculated result with common—used theory and the real situation.To the subgrade section of Wuhan—Guangzhou Passenger Dedicated Line,CFG pile was used to treat the subgrade and the subgrade subsidence deformation was monitored for seeking the subsidence law with the subsidence curves and predicting the subsidence with the curve fitting method.Through the study and analysis,the subsidence behaviors of CFG pile composite subgrade are known.so the reference can be offered to the construction.
Research conclusions: The following conclusions can be obtained from the study on subgrade subsidence deformation and the prediction of the subgrade subsidence of Wuhan—Guangzhou Passenger Dedicated Line with the curve fitting method:The total subsidence in the subgrade center is bigger than that in the right and left subgrade shoulders and the total subsidence curve in the subgrade center is basically consistent with the grade rate of curve of right and left subgrade shoulders.The biggest subsidence is not in the subgrade center,but in the place 1—2 m away from the subgrade center.The predicted results with double curve fitting method and exponential curve fitting method are over big and the predicted result with three—point method iS over small.However.the predicted result with Asaoka method is mediated with no especial requirement of prediction time and hiigh accuracy.The subsidence can be controlled well by adopting CFG pile composite foundation.
2009 Vol. 26 (5): 5-7 [
Abstract
] (
2551
)
HTML
(1 KB)
PDF
(360 KB) (
308
)
8
Analyses of Internal Force for the Deformation of Foundation Pit of High Building and Optimum of Measurement Spot
LI Feng—chao
Research purposes: The stability of foundation pit of high building relates closely to the deformation of exterior—protected construction,soil condition and hydrographic condition.The surface subsidence and wall displacement can be controlled effectively if the deformation,soil and hydrographical conditions are treated well.This paper analyzes the distribution regulation and influence factors of the displacement of the foundation pit during excavation through optimal distribution of the measurement spots based on the mathematical statistical principle and with the help of the simulation calculation result of the excavation with finite element,and offers the optimal program for distribution of measurement spots based on the principle of reducing the measurement error for providing the basis for the construction.
Research conclusions: Through the analyses the deformation of strip exterior—protected construction for foundation pit,optimum of measurement spots and analyses of the measured data,the followings are concluded:(1)The horizontal displacement of the exterior—protected construction depends on the excavation depth,width of foundation pit,soil nature,wall rigidity and embedded depth.(2)The measurement spots for the displacement of the wall top should be installed from the span center to both sides evenly,and the measurement spots for the wall should be installed at the supporting place of slightly higher than the deep excavation place with the beginning from the center and from top to bottom.(3)The real—time monitoring should be done in the course of the excavation for predicting the deformation regulation,taking preventive measures in time,lowering the deformation speed and guaranteeing the optimum of measurement spots and the construction safety.
2009 Vol. 26 (5): 8-11 [
Abstract
] (
3706
)
HTML
(1 KB)
PDF
(402 KB) (
136
)
12
Treating Methods for the Displacement of Reinforcing Cage and Pile Breaking in Bored and Cast—in—place Pile Work
SHEN Zhong一wu
Research purposes: Bored and cast—in—place pile is widely used in construction and it belongs to concealed work,but sometimes the quality problems or quality accidents occur in the work.The experience and statistic data show the displace of reinforcing cage is the quality problem that the most probably occurs and the pile breaking is the quality accident that the most probably Occurs in bored and cast—in—place pile work.80 this paper researches the treating methods for the displacement of reinforcing cage and pile breaking in bored and cast—in—place pile work.
Research conclusions: The researches and applications show the”Floating Method”and”Rolling Pad Method”can effectively solve the problem of the displacement of reinforcing cage with the characteristics of fast and easy operation and no adding investment.The”Duct Fetching Grout Method”can be used for the pile breaking in the cause of grouting, but it is necessary to fabricate the grout collector before the pile foundation construction.The twice as much can be accomplished with half the effect if the condition is possible.In this way,the accident possibility can be reduced much.
2009 Vol. 26 (5): 12-15 [
Abstract
] (
2546
)
HTML
(1 KB)
PDF
(179 KB) (
296
)
16
Research on the Performances of U77 MnCr Used for Heavy—haul Railway
LIU Feng—shou,ZHOU Qing—yue,ZHANG Yin—hua,CHEN Zhao—yang
Research purposes: The heavy—haul railway of foreign countries has successfully used the low—alloy rails containing Cr.but there was no application of low—alloy rails containing Cr in Chinese heavy haul railway in tIIe past.The parent metals and welding of U77 MnCr rail as well as the application of U77 MnCr rail ale studied in this paper.
Research conclusions: The parent metals of U77 MnCr rail is suitable for being used in the straight section of heavy—haul railway because of its high purity and good strength—toughness,has a perfect cost performance because it only contains the cheap chrome alloy of 0.25%一0.40%with good elasticity and does not contain the treasure vanadium alloy,has a good welding performance with self—harden ability of welding joints,SO it does not need air cooling after normalizing and the toughness of the rail top surface matches the toughness of the parent mental,and has a good fatigue resistance that can prolong the service life of the rail on heavy—haul railway.
2009 Vol. 26 (5): 16-20 [
Abstract
] (
2535
)
HTML
(1 KB)
PDF
(405 KB) (
226
)
21
Research on the Improving the Accuracy of Free—positioning Electric Total Station for Track Measurement
ZHU Hong—tao,WU Wei—jun,WANG Zhi—yong
Research purposes: ith the speed—raise of train in China,higher standards are demanded for layout and maintenance of railway track.The goal of layout and maintenance of railway track with higher standards can be achieved by improving the accuracy of track measurement.Positioning electric total station is the preparation work for the track measurement for passenger dedicated line and also the key step for improving the accuracy of track measurement.This paper studies the methods of improving the accuracy of free—positioning electric total station.
Research conclusions: This paper mainly studies the intermediate angle consummation method and the program compensation method for track measurement with electric total station.The study and practice show these two methods are helpful for improving the accuracy of positioning electric total station.The intermediate angle consummation method is recommended when the environment is good and the program compensation method is recommended when the environment is bad.However,these two methods can be used together,which can further improve the the accuracy of free—positioning electric total station.
2009 Vol. 26 (5): 21-23 [
Abstract
] (
2474
)
HTML
(1 KB)
PDF
(137 KB) (
184
)
24
Quality Control Technology and Measure for Double—slab Ballastless Track
ZHAO Dong—tian
Research purposes: The ballastless track is the preferred track structure for high—speed railway.In order to make the double—slab ballastless track meeting the requirements of 3 D positioning,high track regularity and less maintenance,the quality control technology and measure in three construction phases for double—slab ballastless track are offered based on the researches on the chosen construction program for the purpose of meeting the accurate demand of the track.
Research conclusions: It is concluded from the research the key points of quality control for double—slab ballstless track can be seized through choice of the construction programs,and the construction procedure and technique can be improved by analyses of the data of the technique tests and the other tests done before the construction.Upon it the engineers can fully master the quality control technology and measure for double—slab ballastless track for improving the construction quality and track accuracy.
2009 Vol. 26 (5): 24-27 [
Abstract
] (
2559
)
HTML
(1 KB)
PDF
(438 KB) (
267
)
28
Research on the Key Technology for Laying CRTS I Slab Track of 350 km/h Passenger Dedicated Line
DONG Chong—feng
Research purposes: The CRTS I Slab Track in the experimental section of Wuhan—Guangzhou Passenger Dedicated Line is the first time to be used on the 350 km/h railway line in China.Through doing the researches on the technologies of track measurement,fine adjustment of track slab,mortar fabricating and grouting,a set of suitable construction technologies and equipments for laying CRTS I Slab track has been summarized for providing the experience to the similar works in future.
Research conclusions: The EMU test with the speed of 35 1 km/h on the experimental line shows the all properties of the slab track satisfy the design requirements and the key technologies for laying the CRTS I Slab Track is successful.The triangular compass and portal frame are used for fine adjusting the slab with fast speed and high accuracy.After adjustment,the elevation error of the top surface of the slab is less than 1 mm,the error between the central line of the slab and the central line of convex retailing stand is less than 1 mm,the gap error between the slab and retailing stand is less than 5 mm. and the high—low regularity and directional regularity between the slabs are less than 2 mm,so the technology can be widely used for laying the slab track.
2009 Vol. 26 (5): 28-30 [
Abstract
] (
2547
)
HTML
(1 KB)
PDF
(546 KB) (
271
)
31
Research on the Transverse Design Parameters for Large-span Rigid--frame Arch Bridge
WU Zai—xin,HE Guo-jing,LUO Shi—dong,YAN Ai—guo
Research purposes: The four improved design programs were proposed for the characteristics of unfavorable transverse stress in preliminary design of Yichang Yangtze River Bridge. By analyses of the influences of design parameters such as the setting position and figuration size of the diaphragm and transverse beam,the mechanisms and efficiencies of each program were revealed comprehensively.Based on the result of parameter analysis,an optimum program Was offered and its mechanism was verified thoroughly.
Research conclusions: :(1)The elastic support of the diaphragm affects the whole load—bearing capacity of the section of box beam to some extent and the transverse beam can easily and directly improve the load——bearing capacity of the roof,SO with consideration of the advantages of each design program,an integrated program should be made to improve the load—bearing capacity of box beam.(2)It can be seen from the change law of axial force of boom that the axial force of the boom in all calculation programs has no change basically.It shows the diaphragm or transverse beam installation only changes the transverse rigidity of box beam and has a little influence on the vertical rigidity of box beam, and it also verifies again the elastic support effect of the diaphragm only changes the force transfer way in the box beam and has no obvious innuence on the rigid ratio of the beam and arch.
2009 Vol. 26 (5): 31-35 [
Abstract
] (
2505
)
HTML
(1 KB)
PDF
(907 KB) (
86
)
36
Analysis and Evaluation of Seismic Behavior of Continuous Girder Bridge
ZHAO Xu—feng,WANG Chun—miao
Research purposes: In order to satisfy the demand of seismic design of continuous girder bridge stipulated in the”Seismic Design Code for Railway Engineering”,based on one calculation example,this paper makes elastic seismic response analysis under frequent earthquakes and elastio—plastic analysis under severe earthquakes for a railway continuous girder bridge(main span:48:80:48 m)and evaluates the seismic behavior of the continuous girder bridge in strength,ductility and shear resistance.
Research conclusions: The checking calculation methods for the strength and stability of the continuous girder bridge under frequent earthquakes and the ductility of the continuous girder bridge severe earthquakes are proposed,which cover the shortage of the Code and provide the theoretical basis for the seismic design and evaluation of the seismic property of the continuous girder bridge.
2009 Vol. 26 (5): 36-39 [
Abstract
] (
2611
)
HTML
(1 KB)
PDF
(254 KB) (
102
)
40
Research on the Static and Dynamic Load Tests for Prestressed Concrete Continuous BOX Girder Bridge
JIANG Chuan-jin
Research purposes: Based on the observing the stress and deformation in the control section and typical position of continuous box girder bridge under different static loads,the actual stress distribution and deformation of the bridge are obtained and based on the testing the actual stress of the bridge,the actual load—beating capacity of the bridge can be assessed and determined for providing measured data for the acceptance check of completion works.
Research conclusions: Through the static and dynamic 10ad tests,the parameters about stress,deformation and frequency of the bridge are obtained.The tests results show the theoretical analysis and calculation method uses for the bridge are feasible,and with which the construction quality can be guaranteed and the rigidity and load bearing capacity of the bridge can meet the requirements of the design and relative standards.
2009 Vol. 26 (5): 40-43 [
Abstract
] (
2518
)
HTML
(1 KB)
PDF
(458 KB) (
178
)
44
Analyses of the Bearing Capacity of Normal Section of Reinforced Concrete Rectangle Girder with Single Reinforcement
WU Ji-jin
Research purposes: Through introduction of economical reinforcement ratio,the relationship between reinforcement ratio,girder sectional dimension and anti—bending capacity is analyzed,the direct formula for estimating girder height for the requirements of bearing capacity of normal section is derived,and the optimum design of the normal section of rectangle girder with single reinforcement is proposed with comprehensive consideration of anti—bending capacity and deflection checking calculation SO as to easily determine reasonable sectional dimension and longitudinal reinforcement quantity.Finally,the impacts of change in longitudinal reinforcement ratio on deflection and maximum crack width and the relationship between reinforcement ratio,ultimate bending moment and the combined bending value under 10ad effect are discussed.
Research conclusions: As sectional design is conducted by means of the direct estimation formula regarding the girder height estimation based on beating capacity of normal section,it not only Call,when meeting the requirements for beating capacity of normal section of girder and economical reinforcement,conduct sectional design by using the limit value of span—height ratio which meets the requirement of deflection control,but also can conduct optimum design of some bending members with large sectional dimension with consideration of control of bearing capacity of normal section and deflection.With the common—used reinforcement ratio scope of q [0.6%,1.5%],the reinforcement ratio based on the ultimate bearing capacity increases with the increase of the load under the condition that girder sectional dimension and material strength remain unchanged.Meanwhile,the mid—span deflection value increases in spite the girder rigidity is improved to some sense.Therefore,upon calculation of maximum crack width,although the increase of load will lead the change of relevant parameters,but the increase of reinforcement ratio can better control the crack width.
2009 Vol. 26 (5): 44-49 [
Abstract
] (
2549
)
HTML
(1 KB)
PDF
(303 KB) (
448
)
50
Research on the Girder Erection at 1 8‰Long Gradient with JQ 160 Bridge Girder Erecting Machine
PAN Sheng—qi
Research purposes: This paper analyzes the characteristics of girder erection at 1 8‰ long gradient with JQ 160 bridge girder erecting machine,mainly verifies the climbing capacity,hauling capacity,braking capacity and remaining the level of machine arias of JQ 160 bridge girder erecting machine,and puts forward the plan for upgrading JQ 160 bridge girder erecting machine for the purpose of meeting the rapid development demands of railway construction.
Research conclusions: Based on the analyses and calculation of the climbing capacity,hauling capacity,braking capacity and remaining the level of machine aiTas of JQI60 bridge girder erecting machine,the plan for upgrading JQ 160 bridge girder erecting machine Was put forward and applied in Bidding WI of Yichang—Wanzhou Railway.This upgrading plan Can expand the applicable scope of JQI60 bridge girder erecting machine can be expanded to 18‰long gradient with meeting the technical and safety requirements of girder erection at 1 8‰ long gradient.
2009 Vol. 26 (5): 50-53 [
Abstract
] (
2611
)
HTML
(1 KB)
PDF
(134 KB) (
121
)
54
Research on the Tunnel Technical Standard under 30t Axis Load
WANG Xiu—ying,GONG Zeng—jin,LIU Wei—ning
Research purposes: For the freight traffic,the heavy haul is the one of the development trends.Now the axis load is 25t in China,the target is 30t in the near future.The increase of axis load will bring the bigger load to the rail and the foundation under the rail,resulting in the increase of tunnel base disease.So it is necessary to study the impact of heavy axis load on the tunnel base and the technical standard for the tunnel under 30t axis load.
Research conclusions: The section design of railway tunnel for heavy haul traffic based on the Taihangshan mountain tunnel for mixed passenger and freight traffic is basically feasible.The simple grate layer should be canceled to the railway tunnel for heavy haul traffic.The invea should be installed when the surrounding rock grade is m or above.The ratio of rise to span and the depth of the invert should not be lower than the standard for passenger dedicated line tunnel.Lots of tests on site and measurements must be done before working out the tunnel technical standard under 30t axis load because of the complexity of train load and variance of the surrounding rock.
2009 Vol. 26 (5): 54-58 [
Abstract
] (
2579
)
HTML
(1 KB)
PDF
(428 KB) (
164
)
59
Functions for the Bearing Capacity of Lining Cross—section of Shield Tunnel
YUAN Yong,ZHAO Qing—li
Research purposes: The duct piece for shield tunnel lining is an eccentric pressed component with failure modes of the pressures on the big and small eccentric centers of the head—on cross—section and the shearing force on the oblique section.The functions expressed by moment of flexion or axial force for the bearing capacity of head—on Cross—section under typical condition were given in the previous study,but they can not fully attribute the working mode of the duct piece.This paper offers many expressions for the functions used for the bearing capacity of the pressures on the eccentric center of the head—on Cross—section and the shearing resistance of the oblique section based on the analytic formulas for the beating capacity and inner force of the duct piece for the shield tunnel lining in order to provide the reliability for calculating the bearing capacity of the cross—section,and evaluates the sensitive factors of the functions for the bearing capacity of the Cross—section of the duct piece.
Research conclusions: With establishing the functions for the bearing capacities of the head—on Cross—section and oblique section of the shield tunnel lining,the analytic formulas for the bearing capacity of head—on Cross—section with big and small eccentric center and shearing resistance of oblique section are offered.The sensitive analyses of the random variations of the functions for bearing capacity are made with an example.It is concluded for the bearing capacity of the head—on cross—section,the sensitivity of random variations is different when using the functions with different expressions,the Pv has the biggest influences on the functions for the bearing capacity of head—on Cross—section oil the arch top,and the f,has the biggest influence on the functions for bearing capacity of the oblique section on the arch web.
2009 Vol. 26 (5): 59-63 [
Abstract
] (
2592
)
HTML
(1 KB)
PDF
(1454 KB) (
118
)
64
Analyses of the Cause for the Fracture of Monolithic Concrete Bed in Tunnel and Treatment Measures
CHENG Xue一wu.DONG Jing
Research purposes: With continuous construction of passenger dedicated line,the ballastless track becomes more and more.However,with the increase of the traffic volume and service life,the roadbed default often occurs in tunnel,which disturbs the traffic safety.Especially the fracture of monolithic concrete bed in the tunnel built in 1960s or 1970s becomes common default.This paper analyzes the causes for the fracture and puts forward the treating measures for tile fracture.
Research conclusions: The fracture of monolithic concrete bed in tunnel has t}le characteristics of concealment.Sudden occurrence and continuity.The causes for the fracture are the dissolution and corruption of underground water,defaults of construction and maintenance and shoItage of maintenance.The measures of dredging underground water,adjusting the track gradient partly and mud jacking can be taken for the fracture.The practices show the perfect result has been got by taking these measures.
2009 Vol. 26 (5): 64-68 [
Abstract
] (
2457
)
HTML
(1 KB)
PDF
(297 KB) (
194
)
69
Study and Application of Curtain Grouting Equipments for Construction of Single Line Tunnel
WANG Xiao-jing
Research purposes: cientific selection of grouting equipments is one of the key points for getting the perfect grouting effect and improving the grouting efficiency.Based on the engineering section size of single line tunnel and the requirements of curtain grouting,the research is done on how to select the grouting equipment that can meet the requirements of grouting materials,grouting technique,environment control and construction schedule,and the analyses of the issues for caution in equipment selection are made for seeking a set of curtain grouting equipments to provide the reference to the similar works.
Research conclusions: The functions and efficiency of the selected equipments have been verified through the application of the selected equipments in curtain grouting for construction of one single line tunnel.The result shows the grouting requirements Can be well met by adopting the imported muhiple—function drilling machine along with China— Made grouting machines.
2009 Vol. 26 (5): 69-73 [
Abstract
] (
2494
)
HTML
(1 KB)
PDF
(412 KB) (
87
)
74
Control Technology for Strata Deformation of Ultra—shallow—buried and Ultra—high Sectional Tunnel with Underground Excavation
ZHANG Zuo—yi
Research purposes: Through the establishment of simulation model based on ANSYS,the two influence laws for control of surface and arch subsidence caused by the strata disturbance due to the excavation of tunnel were researched for control of the unfavorable effects on construction safety and structure stability caused by stress redistribution of strata.The space—time sequence of tunnel excavation was optimized through the comparative analysis of simulation results with measured results and feedback design for construction of the ultra—shallow—buried and ultra—high sectional tunnel with underground excavation under the conditions of complex environment and weak—water rock.
Research conclusions: Compared with the absolute measured deformation,all calculated deformations were in the controlled ranges stipulated in the codes and standards based on the pre—measured and simulated results.Therefore,for construction of ultra—high sectional and ultra—shallow—buried tunnel under the condition of weak—water rock.the establishment of ANSYS simulation model with 100 percent of the stress release by the plane strain mode could meet the demands of the process control and optimization.For construction of the tunnel with CRD method,the simulation results showed that settlement of 2,4,5 and 7 subsections accounted for 85~90 percent of total settlement under the complex conditions.Based on this,the space—time sequence of excavation was optimized in the ways that the excavation method of the reserved cole soil was used along with the stepped CRD method.The sequence was firstly to cut through the upper step is and then to cut through the lower step.The practice has proved that this optimized method is safe and reliable.
2009 Vol. 26 (5): 74-79 [
Abstract
] (
2494
)
HTML
(1 KB)
PDF
(559 KB) (
214
)
80
Construction Technologies for Secondary Lining of the Low Wall and Primary Filling of the Side Arch of Tunnel
LI Shu-jing
Research purposes: Based on the review of the tunnel construction method,the discussion is made on necessities of improvement and innovation of the construction method for secondary lining of tunnel and the introduction is given to the improved construction technology and method for secondary lining of the low wall and primary filling of the side arch of tunnel for the purposes of improving the concrete quality and reducing the construction cost.
Research conclusions: The improved and innovative construction method for secondary lining of railway tunnel simplifies the construction procedure.The problems of bad outlook of secondary lining and water penetrating and leaking in the joint of low wall with side wall can be overcome and the tunnel construction cost call be reduced by adopting these construction technologies.These technologies also can be used in construction of highway tunnel.However.as the new technologies,these technologies need to be verified and improved in more construction practiced.
2009 Vol. 26 (5): 80-83 [
Abstract
] (
2537
)
HTML
(1 KB)
PDF
(250 KB) (
252
)
84
Research on the Track Structure Vibration Induced by Subway Train
LUO Wen—jun,LEI Xiao—yan,WU Ming—hui
Research purposes: The continuous elastic double deck beam model for the track structure is established for analyzing the impacts of different train speeds,track irregularity,and rail pad rigidity and sleeper pad rigidity on track vibrations to provide the technical data for the construction works.
Research conclusions: The studies show the train speed has a significant impact on track structure vibrations.The sleeper vibration speed and the peak value of the reaction of monolithic track bed increase with the increase of the train speed.The track irregularity also has significant impacts on track vibrations.So the routine maintenances of rail wheels tread and rail surface are very important to reduce the track structure vibrations.In addition,the rigidity of rubber pad between sleeper and monolithic track bed has significant impact on track vibrations.The sleeper vibration speed decrease and the reaction of monolithic track bed increase with the increase of the rigidity of rubber pad,but the corresponding spectrum does not change.For the tunnel structure security,the rigidity of rubber pad should be decreased.
2009 Vol. 26 (5): 84-89 [
Abstract
] (
2486
)
HTML
(1 KB)
PDF
(931 KB) (
107
)
90
The Hierarchical Management of Fire Resource of Shenzhen Futian Underground Railway Station and Its Optimizing Design
HAN Feng—yan,XU Zhi—sheng
Research purposes: Shenzhen Futian Underground Railway Station has the characteristics of railway station and subway station and its underground space is not good for the person of suffering fire disaster to be relieved or escape.This paper studies the hierarchical management of the fire resource of underground railway station for the purposes of improving the safety management level and reducing the possibility of firing in underground railway station.
Research conclusions: Combining with the characteristics of service functions and structural style of the Futian Underground Railway Station,the fire resource of the station is identified,and the fire load and scale are analyzed,that is to take 2MW as the scale of luggage firing and manual setting fire,10MW as the scale of shopping fire and 16MW as the scale of train fire.According to the characteristics of underground space structure,the fire dangers in the different areas and the difficulty of evacuating persons,the method for 3 hierarchical management of fire resource is offered on the base of the different fire dangers and adopting the different fire monitoring modes and different management methods for the he different areas.
2009 Vol. 26 (5): 90-93 [
Abstract
] (
2607
)
HTML
(1 KB)
PDF
(175 KB) (
160
)
94
Management System and Characteristics of African Highway Project
CHEN Zhi—jun
Research purposes: On the basis of building No.1 National Highway from Brazzaville to Pointe Notre in Congo,this paper sums up the construction and management system characteristics of the highway project in Africa for providing the experiences to the Chinese enterprises in developing the construction market in Africa.
Research conclusions: The study shows (1)Africa has extensive highway project contracting market.(2)Most of the African highway projects adopt”Design—Build”management system.(3)African highway design mode is more closely combined with the construction site conditions.and the content of design is more complicated and detailed(4)For African highway project,the contractor faces the various risks,SO the Chinese enterprises should fully investigate the situation,and adopt useful measures to reduce the risk to the minimum.
2009 Vol. 26 (5): 94-97 [
Abstract
] (
4784
)
HTML
(1 KB)
PDF
(118 KB) (
457
)
98
Research on the Making Construction Project Schedule with Critical Chain Method
ZHAO Zhen—yu,YOU Wei—yang,LV Qian—lei
Research purposes: Nowadays the construction projects face the limitations of environmental uncertainty and constrained resource.so the method for traditional network planning can not satisfy the demands of increasingly complex construction projects for the feasibility and steadiness.Thus,it is necessary to USe fuzzy critical chain for making the construction project schedule.
Research conclusions: Based on the consideration of the constraints and uncertainties of resources to the construction projects,the new method is offered for making construction project schedule with critical chain method,namely using improved genetic algorithm to identify critical chain,determine the optimal start time of each activity under a desirable schedule and present the algorithm for determining the sizes of the project buffer area and feeding buffer area.The feasible and stable project schedule can be made with this method.because this method integrates the advantages of critical chain method and focuses on the whole project.This method is especially suitable for making the project schedule under the constraints and uncertainty of resources and Call be as an effective tool for making the project schedule.
2009 Vol. 26 (5): 98-102 [
Abstract
] (
2625
)
HTML
(1 KB)
PDF
(364 KB) (
248
)