Abstract:Research purposes:The mode of general design and construction contract was adopted for construction of Line 3 of Shenzhen subway, making great achievements and showing some merits. This paper gives introduction to the merits and demerits of general design and construction contract for the Line 3 of Shenzhen subway to provide the reference to similar works.
Research conclusions:The merits of general design and construction contract for subway construction are as follows: to reduce changes in the design and the construction, save the construction cost, shorten the construction time, be easy to link the design with construction and be helpful for optimizing the design. But there is still room for improvement. For examples, the relative laws and regulations should be revised and improved. The management risk and preventive measures should be studied. How does the government control match its management? How are the relative regulations adaptive to the Bidding Law? And the sample contractor should be studied and worked out.
盛宇平. 地铁3号线设计施工总承包实施之得失[J]. 铁道工程学报, 2010, 27(5): 91-94.
SHENG Yu-ping. Merits and Demerits of General Design and Construction Contract for Line 3 of Shenzhen Subway. 铁道工程学报, 2010, 27(5): 91-94.
Wei Zhongxin, Guan Baihai. General Contracting Project Implementation Cycle-A Case Study of Housing Construction Projects[J]. Journal of Railway Engineering Society, 2009(3): 96-99.
Qi Xiaoming. The Total Project Control Model Reflects the Effectiveness of Risk Management[J]. Journal of Railway Engineering Society, 2008(9): 100-103.
[ 10 ] 王立国, 等. 投资项目评估学[M]. 大连: 东北财经大学出版社, 1998.
Wang Liguo, et al. Investment Project Appraisal[M]. Dalian: Dongbei University of Finance Press, 1998.