Abstract:Research purposes: The Shizhiyang tunnel of Guangzhou—Shenzhen—Hong Kong High—speed Railway underpasses through the main channel of the Pearl River.When TBM tunnelled in the uneven stratum near the Pead River dam in the direction of the tunnel portal,the ground collapse occurred in large scale,endangering the safety of the Pearl River dam.At the sanle time.TBM could not moved.To resolve this problem,the research Was done on choosing the optimal construction scheme and using above 50 m deep long sleeve—valve—pipe to reinforce the stratum.The feasible methods and measures were offered for guaranteeing the construction conducted smoothly.
Research conclusions: The stratum reinforcement scheme and the sleeve—valve—pine technology presented in this research could solve the problem that the core of the deep sleeve--valve—pipe was stuck or fallen when grouting and the problem that the TBM Was probably packaged when grouting in front of TBM.With improving the stratum by grouting,TBM could work normally.
彭 峰,刘广均. 狮子洋隧道下穿珠江大堤注浆加固技术研究[J]. 铁道工程学报, 2010, 27(7): 55-59.
PENG Feng,LIU Guang—jun. Research on Sleeve—valve—pipe Grouting Technology for Reinforcing the Pearl River Dam Underpassed by Shiziyang Tunnel. 铁道工程学报, 2010, 27(7): 55-59.
Editorial Committee of Engineering Geological Handbook Engineering Geological Handbook [K]. The Third Edition. Beijing: China Building Industry Press, 2004.
Zhang Mingqing, Huang Hongjian. Technology for Blocking Water by Grouting for High Pressure Granny Water of Qiyueshan Tunnel[J]. Journal of Railway Engineering Society, 2010(1): 71 -72.
Zhang Minqing, Zhang Wenqiang, Jiang Cairong. Improvement and Application of the Sleeve -valve - pipe Grouting Construction Method [J ]. Construction Technology, 2003(9): 4 -6.
[8] 袁辉.袖阀管注浆加固深层土技术[J].市政技术, 2005 (6): 65 -67.
Yuan Hui. Injection Grouting Technique of Deep -level Soil Stabilization by Sleeve Valve [J]. Municipal Engineering Technology. 2005(6): 65 -67.