铁路隧道工程地下水风险评估探析

许增荣

铁道工程学报 ›› 2011, Vol. 28 ›› Issue (6) : 39-43.

PDF(465 KB)
PDF(465 KB)
铁道工程学报 ›› 2011, Vol. 28 ›› Issue (6) : 39-43.
路网研究

铁路隧道工程地下水风险评估探析

  • 许增荣
作者信息 +

Discussion and Analysis of Underground Water Risk Evaluation for Railway Tunnel

  • XU Zeng - rong
Author information +
文章历史 +

摘要

研究目的:隧道风险评估是一项新近开展的、多专业综合进行的工作,本文是对隧道水文地质风险评估工作意义、内容、方法、要点的分析和探索。
研究结论:风险性评估是在目前勘察手段有限的条件下正确评价地下水风险的合理选择; 本文提出的以概率分析为基础的地下水风险评估是以往以定量计算为重点的水文地质条件评价的重要延伸和完善; 地下水涌水量及涌水方式、地下水压力、地下水变化导致产生围岩稳定问题、水质改变、地下水疏排导致的环境改变是地下水风险的主要因素; 水文地质计算中常因地下水富水性不均导致局部出现较明显误差,风险性评估能够减小这种误差导致局部重大涌水未能预测出现的风险。

Abstract

Research purposes:The underground water risk evaluation for railway tunnel is the work that is done recently and involved in many specialties. This paper analyzes and discusses the significance,contents,methods and main point of the risk evaluation of hydrogeology for railway tunnel.
Research conclusions:The risk assessment is the reasonable way for correcting assessing the risk of the underground water under the condition that the current survey means is limited. The risk assessment of the underground water based on probability analysis presented in this paper is the important development and improvement of the previous assessment of hydrogeologic condition by taking quantitative calculation as the key point. The main factors of the underground water risk include the unstable surrounding rock and change of water quality caused by the volume and way of water bursting,the pressure of the underground water and the change of the underground water as well as the environment change caused by draining the underground water. The obviously local error often happens in the calculation of the hydrogeologic condition because of the uneven watery of the underground water. Conducting the risk assessment can reduce the risk of the big local water bursting caused by the error.

关键词

隧道 / 地下水 / 风险评估 / 水文地质

Key words

tunnel / underground water / risk evaluation / hydrogeology

引用本文

导出引用
许增荣. 铁路隧道工程地下水风险评估探析[J]. 铁道工程学报, 2011, 28(6): 39-43
XU Zeng - rong. Discussion and Analysis of Underground Water Risk Evaluation for Railway Tunnel[J]. Journal of Railway Engineering Society, 2011, 28(6): 39-43
中图分类号: U452.11   

参考文献

[1] 铁建设[2007]200号,铁路隧道风险评估与管理暂行规定[S].
Railway Construction[2007]No.200,The Interim Provisions of Railway Tunnel Risk Evaluation[S].
[2] R.A.弗里择,J.A.彻里.地下水[M].北京: 地震出版社,1987.
R. A. Freeze,J.A.Cherry.Ground Water [M]. Beijing: Earthquake Publishing House,1987.
[3] 张炜,等. 岩溶隧道涌突水原因分析及治理技术探讨[J]. 隧道建设,2008(6) :258-262.
Zhang Wei,etc. Cause Analysis and Countermearsures for Water Gushing of Karst Tunnels [J].Tunnel Construction,2008(6) : 258-262.
[4] 李苍松,何发亮,陈成宗.渝怀线武隆隧道岩溶涌水量计算新方法[J].中国铁道科学,2005(9) :41-46.
Li Cangsong,He Faliang,Chen Chengzong.New Calculation Method of Water Inflow Quantity in Wulong Tunnel on Chongqing-Huaihua Railway[J]. China Raiway Sicene ,2005(9) : 41-46.
[5] 许增荣. 构造深度及其与山区基岩裂隙水的关系[J]. 铁道工程学报,2001(3) :92-95.
Xu Zengrong.Structure Depth And Its Relation With Fissure Water In Basic Rock at Mountinous Regions [J].Journal of Railway Engineering Society,2001(3) : 92-95.
 

PDF(465 KB)

5088

Accesses

0

Citation

Detail

段落导航
相关文章

/