Research on Scheme for Introducing Harbin—Mudanjiang Passenger Dedicated Line into Harbin Region
LiU Meng1,CHI Mo—ran2
1.The Third Railway Survey and Design Institute Group Corporation,Tianjin 300142,China;2.Tianjin Municipal Engineering Design and Research Institute,Tianjin 300000,China
Abstract:Research purposes:The research was done on the scheme for introducing the Harbin—Mudanjiang Passenger Dedicated Line into Harbin region on consideration of the factors of the engineering investment,passage integrity,passenger transport function,coordination with city planning,environmental impact,and the topographic and geol0gical conditions in order to make the scheme more reasonable in technology and economy for obtaining the best comprehensive social benefits.The ideas on the railway alignment can be as the reference to introducing the passenger dedicated line into the big terminal.
Research conclusions:(1)If the line is introduced into the Harbin West Station through the existing railway line,although it needs more investment and has more moving works to be done,but it coordinates with the network planning and the urban construction planning, and the train from the southeast direction via the other lines can enter into the Harbin West Station for convenient Passenger transfer. (2)If the line is introduced into the Harbin West Station from the south.although the line length is shorter and the less investment is needed,but the line cuts the city proper and it can not meet the requirements of the network planning and the urban construction planning.
刘猛,迟默然. 哈牡客专引入哈尔滨地区方案研究[J]. 铁道工程学报, 2012, 29(12): 1-4.
LiU Meng,CHI Mo—ran. Research on Scheme for Introducing Harbin—Mudanjiang Passenger Dedicated Line into Harbin Region. 铁道工程学报, 2012, 29(12): 1-4.
The Third Railway Survey and Design Institute Group Corporation.Feasibility Study of Haerbin—Mudanjiang Passenger Dedicated line[R].Tianjin:The Third Railway Survey and Design Institute Group Corporation,2009.
Xie Zhihong.General Alignment of Hangzhou—Changsha Section on Shanghai—Kunming Railway Passenger Dedicated Line[J]. Railway Standard Design,2009(8):4—7.
[3] 张珂.张唐铁路承德至唐山段线路走向方案研究[J].铁道工程学报,2009(12):1—4.
Zhang Ke.Research on the Trend Line Program for Tangshan—Zunhua of the Zhangtang Railway[J].Railway Standard Design,2009(12):1—4.
[4] 杨军.石武客运专线邯郸站站位方案研究[J].铁道标准设计,2010(9):22—24.
Yang Jun.Scheme on Location of Handan East Railway Station on Shijiazhuang—Wuhan Passenger Dedicated Line,2010(9):22—24.
[5] 金占东.山西中南部铁路通道吕梁山越岭选线研究[J].铁道勘察,2009(6):79—80.
Jin Zhandong.Route Selection of Railway Passage Line Crossing Lvliang Mountain in Central South of Shanxi[J].Railway Investigation and Surveying,2009(6):79—80.
[6]廖开再.石济铁路客运专线引入德州地区方案研究[J].铁道标准设计,2009(8):1—3.
Liao Kaizai.Scheme on Shijiazhuang—Jinan Railway Passenger Dedicated Line Leading into Dezhou Area[J].Railway Standard Design,2009(8):1—3.
[7] GB 50091--2006,铁路车站及枢纽设计规范[S].
GB 50091--2006,Code for Design of Railway Station and Terminal[S].
HuZiping.Design on Comprehensive Route Selection of Yichang — Wanzhou Railway in Complicated Mountainous Area[J].Railway Standard Design,2010(8):33—36.
Peng Xueli.Comparison and Selection for Designing Scheme on Route Lines at Complicated Unfavorable Geological Section on Yichang—Wanzhou Railway[J]. Railway Standard Design,2010(8):37—40.
[10] GB 50090--2006,铁路线路设计规范[S].
GB 50090--2006,Code for Design of Railway Line[S].