Abstract:Research purposes: The earthing design idea is discussed in this paper for a newly - built traction substation on Xiamen - Shenzhen Railway with complex topographic and geologic conditions and high soil resistivity based on meeting the contact potential and step potential conditions in combination with requirements of current railway codes and IEEE standards concerned. At the same time,an optimal scheme is selected by comparison of economic benefits, providing a reference for the earthing design with similar soil resistivity condition.
Research conclusions:A proper earthing scheme should be adopted for the traction substation in consideration of local conditions. The earthing resistance of the substation may be increased to some extent upon verifying the contact potential and step potential. On the basis of this,different resistance reducing measures can be adopted for saving investment of the project under the premise of ensuring equipment and personnel safety.
侯 峰 侯蜀君. 高土壤电阻率地区牵引变电所接地设计[J]. 铁道工程学报, 2012, 29(6): 71-73.
HOU Feng,HOU Shu - jun. Earthing Design of Traction Substations in Regions with High Soil Resistivity. 铁道工程学报, 2012, 29(6): 71-73.
Wu Guangning, Ren Xiaona,Fu Longhai,etc. The Study of Lightning Protection and Grounding Technology about High - speed Railway [C]/ /Institute of China Railway Electrification Board, Conference Proceedings,2006.
[4] DL/T 621—1997,交流电气装置的接地[S].
DL /T 621—1997, Groungding for AC Electrical Insfallations[S].
[5] 王洪泽,杨丹,王梦云. 电力系统接地技术手册[K]. 北京:中国电力出版社,2007.
Wang Hongze,Yang Dan, Wang Mengyun. Electric Power System Grounding Technical Manual [K]. Beijing:China Electric Power Press,2007.
Wang yong. Research of the Short – circuit Test of Traction Power System on the Passenger Dedicated Line [J]. Journal of Railway Engineering Society,2009(11): 76 - 80.
[7] 杨岗. 客运专线综合接地系统方案研究[J]. 铁道工程学报,2006(7):76 -80.
Yang Gang. Program Research on Integrated Grounding System for Passenger Dedicated Line [J]. Journal of Railway Engineering Society,2006(7):76 - 80.