Abstract:Research purposes: The total length of existing railway line with speed raising to 200 km/h will be expanded to 6003 km in China after six-round speed up. Compared with the low-speed line,200 km/h line requires more strict track maintenance,especially in China track maintenance should meet the requirements of existing line with speed raising to 200 km/h for mixed running of 200 km/h motor train set , 120 km/h freight train and double deck container train with axle load of 25 t. The analysis is made for the train-shaking phenomenon from the fourteen problems found in several experiments for six-round speed up,the rethink is made on the common problems existed in the areas of design,construction,acceptance and maintenance,and the issues necessary for being further studied are presented primarily for track maintenance in areas of inspection,operation,repeated inspection,safety , management and training , in order to make workers of track maintenance to fit in with high standard and requirements of 200 km/h for high regularity.
Research Conclusions: In order to meet the high requirement of 200 km/h line,the primary countermeasures are proposed for track maintenance,including inspection , operation , strengthening management of rail , track structure, inspection of long slope,large-sized machine maintenance,ballast management , solving the problems of curve,switch position and slope improperly , testing and deciding tolerance values of dynamic and static irregularity of 200 km/h line, strengthening person training , establishing all kinds of systems and regulations,guaranteeing skylight subgrade drainage and well doing the protection work of track. Also the issues necessary for being further studied are proposed,including introduction of large-sized machines and their match,research and development of inspectional and operational tools under static status,finding out the law of preventive grinding , finding out the law of subgrade settlement in order to guarantee the even of transition area,improving rigidity of bridge against disturbance deformation,taking overall measures in the areas of design,fabricating and construction for improving the regularity of switch structure and switch area and the vibration on bridge and bridge fatigue caused by 200 km/h train.
胡华锋. 既有线提速至200 km/ h工务存在的问题及其对策[J]. 铁道工程学报, 2007, 24(1): 96-101.
HU Hua-feng. Problems in Track Maintenance of Existing Railway Line with Speed Raising to 200 km/h and Its Countermeasures. 铁道工程学报, 2007, 24(1): 96-101.