Abstract:Research purposes: The analyses were made for the prediction of the settlement of the CFG pile composite foundation of one passenger dedicated line predicted with the hyperbolic graphic method, the hyperbolic method, three- point method and the index method. The actual measured settlement data were polished by using quintic multinomial By doing so, the error produced in the measurement and the non-isochronism of the actual measured settlement data can be eliminated and it can provide the reference to the similar works.
Research conclusions: Application of the interpolation of the quintic multinomial can eliminate the error caused by environment factors and the difficulty in selection of measurement spot caused by the non-isochronism in measurement to make the settlement curve smooth. From the prediction results obtained from the four methods mentioned above it can be seen the result obtained from the three- point method is good, getting the max imum relative coefficients while the measured values obtained from the hyperbolic method are the biggest.
汪 江, 卢国胜. 客运专线 CFG桩复合地基沉降预测分析[J]. 铁道工程学报, 2010, 27(11): 1-4.
WANG Jiang, LU Guo-sheng. Analysis of Prediction of Settlement of CFG Pile Composite Foundation of Passenger Dedicated Line. 铁道工程学报, 2010, 27(11): 1-4.
Xue Xinhua. Study on Prediction of Bearing Capacity of CFG Pile Composite Foundation with ANFIS [ J ]. Journal of Railway Engineering Society, 2010(5): 42 - 47.
LI Fan. Study on Method of Calculating the Final Settlement of Soft soil Embaarkment[J]. Journal of Hefei University of Technology (Natural Science), 2003(4): 278 -280.
Ning -Hang Ltd. Company. Ning -Hang Passenger Dedicated Railway Line Observation and Assessment of Settlement Project Implem entation Details [ Z ]. Hangzhou:Ning -Hang Ltd. Company, 2009.
[8] Wang Haiming, etc. For Reconstructed Railway from Shimen to Changsha Pre-feasibility to Add Second Line [ R]. Wuhan: China Railway Siyuan Survey and Design Group Co. Ltd, 2008.
Yang Dong, etc. Double Lines Pre-feasibility for Reconstructed Railway from Ganzhou to Longyan [ R ]. Wuhan: China Railway Siyuan Survey and Design Group Co. L td, 2008.