Abstract:Research purposes: According to the current situations,topographic conditions and geological conditions along the railway from Nanjing to Xihn(Nanyang—Hefei district),the recommended speed target value for upgrading Nanjing—Xi’an Railway is offered after making analyses of the railway functions.traffic demands and matching relation with neighbour railway and comparing many schemes in technology and economy.
Research conclusions: The speed target value for upgrading Nanjing—Xi’an Railway increases to 160 km/h because the topographty along the railway is flat,the minimum track curve radius is 1 600 m or above.In addition,dong so is to avoid bigger dismantling and changing for the railway and save the investment.The speed target value of 1 60 km/h is also designed for the additional second track of the railway to well match the existing track and neighbour railway according to the functional orientation of the railway that mainly undertakes freight transportation and simultaneously undertakes passenger transportation.
杨元明. 宁西铁路(南合段)扩能速度目标值研究[J]. 铁道工程学报, 2010, 27(8): 7-11.
YANG Yuan—ming. Research on Speed Target Value for Upgrading Nanjing—Xi"an Railway (Nanyang—Hefei Section). 铁道工程学报, 2010, 27(8): 7-11.
[1] 铁道第四勘察设计院.改建铁路湘桂线衡阳至永州段扩 能提速工程预可行性研究[R].武汉:铁道第四勘察设计 院, 2003. Fourth Survey and Design Institute of Railway. Pre - feasibility Study for Rebuilt Xiang-Gui Railway Project from Hengyang to Yongzhou by Increasing Capacity and Speedup [R ]. Wuhan: Fourth Survey and Design Institute ofRailway, 2003.
[2] 中铁第四勘察设计院集团有限公司.改建铁路石门至长沙线增建第二线工程预可行性研究[R ].武汉:中铁第四勘察设计院集团有限公司, 2008.
China Railway Siyuan Survey and Design Group Co.Ltd. Rebuilt Railway Pre-feasibility Study for Newly Built Second line from Shimen to Changsha [R ].Wuhan: China Railway Siyuan Survey and Design Group Co.Ltd, 2008.
[3] 中铁第四勘察设计院集团有限公司.改建铁路娄底至邵阳扩能改造工程预可行性研究[R ].武汉:中铁第四勘察设计院集团有限公司, 2008.
China Railway Siyuan Survey and Design Group Co.Ltd. Rebuilt Railway Pre-feasibility Study for Increasing Capacity from Loudi to Shaoyang [R ].W uhan: China Railway Siyuan Survey and Design Group Co.Ltd, 2008.
[4] 铁一院.铁路工程设计技术手册(线路)(修订版) [K ].北京:中国铁道出版社, 1994.
FSDI. Technological Handbook for Design of Railway Engineering (Route) (Revised Edition) [K ]. Beijing: Chinese Railway Publishing House, 1994.
[5] GB 50090)2006,铁路线路设计规范[S].GB 50090)2006,Code for Design ofRailway L ine[S].
[6] 中铁第四勘察设计院集团有限公司.改建铁路宁西线南阳至合肥段增建第二线工程预可行性研究[R].武汉:中铁第四勘察设计院集团有限公司, 2008.
China Railway Siyuan Survey and Design Group Co.Ltd. Pre-feasibility Study for Rebuilt Railway andNewly Built Second Line from Nanyang to Hefei [R ].Wuhan: China Railway Siyuan Survey and Design Group Co.Ltd, 2008.
[7] 中铁第四勘察设计院集团有限公司.改建铁路皖赣线增建第二线工程预可行性研究[R].武汉:中铁第四勘察设计院集团有限公司, 2008.
China Railway Siyuan Survey and Design Group Co.Ltd. Rebuilt Wan -Gan Railway Pre-feasibility Study for Newly Built Second Line [R ]. Wuhan: China Railway Siyuan Survey and Design Group Co. Ltd,2008.
[8] 魏州泉.包西铁路通道改建方案研究[J].铁道工程学报, 2010(6): 1 -4.
Wei Zhouquan. Study on Scheme for Reconstruction of Baotou -Xi 'an Railway Corridor [ J ]. Journal of Railway Engineering Society, 2010(6): 1 -4.
[9] 黄远清.珠三角城际轨道交通正线线间距研究[J].铁道工程学报, 2010(6): 23 -26.
Huang Yuanqing. Studuon Midway between Tracks of Main Line of Intercity Rail Transit in Pearl River Delta Zone[J]. Journal of Railway Engineering Society, 2010 (6): 23 -26.
[10]中铁第四勘察设计院集团有限公司.改建铁路赣龙铁路复线预可行性研究[R ].武汉:中铁第四勘察设计院集团有限公司, 2008.
China Railway Siyuan Survey and Design Group Co.Ltd. Rebuilt Railway Pre -feasibility Study for Double Lines from Ganzhou to Longyan [R ]. Wuhan: China Railway Siyuan Survey and Design Group Co. Ltd,2008.