Abstract:Abstract:Research purposes: In the shield construction, there is strong coupling in the interaction between shield machine and rock-soil mass, so the research on numerical simulation about the impact of various factors will become necessary. Combined with geological conditions and on-site monitoring data, the research on shield tunneling of 202 bid section of Dalian metro is carried out to analyze the influenting factors and effect of surface settlement by three-dimensional finite element.
Research conclusions:The following conclusions are proposed: (1) The surface settlement decreases with the increasing of the earth pressure, and the stress or plastic zone of tunnel face increases. (2) The surface settlement decreases with the increasing of grouting capacity, but excessive grouting capacity will destroy the self-stability of soil, which makes surface settlement increase. (3) When shield machines cross the different soil layers, the parameters can be adjusted according to simulation results. (4) The research results can monitor metro shield tunnel under the complicated environment.
于德海 张 涛 姜谙男. 复杂条件下地铁盾构施工过程的影响因素分析[J]. 铁道工程学报, 2015, 32(5): 86-.
YU De-hai,ZHANG Tao,JIANG An-nan. Analysis of Influencing Factors of Metro Shield Construction under Complicated Conditions
[1]周宁,袁勇. 越江盾构隧道纵向结构分析模型的改进及应用[J]. 中国矿业大学学报,2010(2):208-213.
Zhou Ning,Yuan Yong. An Improved Longitudinal Structure Model of Cross-river Shield Tunnel and Its Application[J]. Journal of China University of Mining &Technology,2010(2): 208-213.
[2]郑宜枫,丁志诚,戴仕敏. 超大直径盾构推进引起周围土体变形和土水压力变化分析[J]. 地下空间与工程学报,2006(8):1349-1353.
Zheng Yifeng,Ding Zhicheng,Dai Shimin. An Analysis of Surrounding Ground Deformation and Ground/Water Pressure Fluctuations Caused by a Super-Large DiameterTBM[J]. Chinese Journal of Underground Space and Engineering,2006,2(8): 1349-1353.
[3]岳中文,杨仁树,孙中辉,等. 厚砾石层斜井开挖围岩破坏机理模型试验研究[J]. 中国矿业大学学报,2011(4):368-372.
Yue Zhongwen,Yang Renshu,Sun Zhonghui,etc. Experimental Study of The Failure Mechanism in Surrounding Rock of an Inclined Shaft Excavated Through a Thick Gravel Stratum[J]. Journal of China University of Mining & Technology,2011(4):368-372.
[4]殷加顺. 盾构施工注浆对地层变形影响的有限元模拟及试验研究[D]. 天津:天津大学,2009.
Yin Jiashun. Simulation and Test Research of Shield Groutingon Ground Deformation Effects of Finite Element[D]. Tianjin:Tianjin University,2009.
[5]HOWARTH D F,ROXBOROUGH F F. Some Fundamental Aspects of Disc Cutters in Hard Rock Excavation[J]. S. Afr. Inst. of Min. Metall,1982(2):309-315.
[6]WIJK G. A model of Tunnel Boring Machine Performance[J]. Journal of Geotechnical and Geological Engineering,1992(1):19-40.
[7]龚秋明,赵坚,张喜虎. 岩石隧道掘进机的施工预测模型[J]. 岩石力学与工程学报,2004(S2): 4709-4714.
Gong Qiuming,Zhao Jian,Zhang Xihu. Performance Prediction of Hard Rock TBM Tunneling[J]. Chinese Journal of Rock Mechanics and Engineering,2004(S2):4709-4714.
[8]刘明月,杜彦良,麻士琦. 地质因素对TBM掘进效率的影响[J]. 石家庄铁道学院学报,2002(4):40-43.
Liu Mingyue,Du Yanliang,Ma Shiqi. Analysis of Relationship between Geologic Condition and the Efficiency of TBM Boring[J]. Journal of Shijiazhuang Railway Institute,2002(4):40-43.
[9]张厚美,吴秀国,曾伟华. 土压平衡式盾构掘进试验及掘进数学模型研究[J]. 岩石力学与工程学报,2005(S2):5763-5766.
Zhang Houmei,Wu Xiuguo,Zeng Weihua. Study on Tunneling Experiment and Mathematical Model of EPB Shield[J]. Chinese Journal of Rock Mechanics and Engineering,2005(S2):5763-5766.
[10]张鹏. 盾构隧道管片施工力学性能三维数值模拟研究[J]. 铁道工程学报,2012(7):63-69.
Zhang Peng. Research on Mechanical Property of Segment of Shield Tunnel during Construction With Three-dimensional Numerical Simulation[J]. Journal of Railway Engineering Society,2012(7):63-69.