Abstract:Pre-stressed concreted simple-supported beam pre-casting with 24 m pre-tensioned broken-line reinforcement is a new type structure which is first adopted at home and one of the new technologies adopted on Qinghai-Tibet Railway,with high technical level,new construction technique and great construction difficulties. Based on its technological features and construction requirement, the techniques for pre-stressed concrete and the control value of durable concrete construction are well worth spreading to use and studying.
和民锁,马新安,曹新刚. 大跨度先张法折线配筋预应力 混凝土简支梁预制施工技术[J]. 铁道工程学报, 2004, 21(2): 43-45.
HE Min-suo, MA Xin-an,CAO Xin-gang. CONSTRUCTION TECHNIQUE OF PRE-CASTING FOR PRE-STRESSED CONCRETE SIMPLE-SUPPORTED BEAM WITH LONG SPAN PRE- TENSIONED BROKEN-LINE. 铁道工程学报, 2004, 21(2): 43-45.