Abstract:During the construction of the cast-in-place concrete continuous beam on the soft foundation, the key questions are how to control the settlement of subsoil and make the pre~ determined camber within the extent of design,and prevent the beam from the distress etc caused by scaffold’s deformation which is caused by the subsoil’s settlement. Based on this, the paper discusses the way how to control the foundation’s settlement and make the con?struction of cast-in-place concrete continuous beam doing well.
尤昌龙,袁松,庄季栋. 软土地区现浇混凝土连续梁的实践 —软土地基处理[J]. 铁道工程学报, 1997, 14(3): 123-128.
You Changlong Yuan Song Zhuang Jidong. PRACTICE OF CAST-IN-PLACE CONCRETE BEAM ON SOFT FOUNDATION. Journal of Railway Engineering Society, 1997, 14(3): 123-128.