Abstract:Research purposes : The suspension and fixing of the catenary under upper cover platform are different from those with the existing methods because they need to consider the impact of upper cover platform. Therefore, it is necessary to do the research on the impacts of the civil engineering requirements, construction difficulty, installation period and maintenance convenience requirement on the suspension and fixing of the catenary under the upper cover platform to determine the available catenary suspension and fixing modes under the upper cover platform.
Research conclusions : The research was done on the suspension and fixing of the catenary under the upper cover platform of the Tanglang Vehicle Depot of Shenzhen metro on learning the suspension and fixing modes of the catenary in the high - speed railway tunnel. From the research,it is concluded : (1) The crossing suspension mode should be adopted to the catenary under upper cover platform of metro vehicle depot. (2) The structure of the embedded C shaped steel (channel) should be adopted to the catenary under the upper cover platform on determination of the technical parameters and requirements of the C shaped steel embedded parts. (3) The design plans of the various embedded parts corresponding to the contacting suspension and fixing (crossing fixing cable, hoist cable and cantilever, etc) and installation of the anchor and isolation switch were determined on the research. (4) From the angle of the project management, the analysis was made for the advantages of the structure of embedded C - shaped steel mode for the catenary’s suspension and fixing. The proposal was made that this mode would be widely used in the catenary engineering.
侯茂华. 地铁车辆段上盖平台下接触网悬挂固定研究[J]. 铁道工程学报, 2013, 30(7): 70-73.
HOU Mao-hua. Study on Suspension and Fixing of Catenary under Upper Cover Platform of Metro Vehicle Depot. 铁道工程学报, 2013, 30(7): 70-73.
Zhang Boyang, Yan Shaofa, Ren Hao. Construction Control Technology for Precast Channel for Catenary in Tunnel of High - speed Railway [J ] .Journal of Railway Engineering Society,2012(9) :75 - 79.
Tian Guanghui, Jue Ming,Chen Yong,etc. Research on Suspension and Fixed Modes of Catenary in Tunnel[ J]. Journal of Railway Engineering Society,2012 (8) :71 - 76.
[3] GB 50157—2003,地铁设计规范[S].
GB 50157—2003,Code for Design of Metro[S].
[4]吕继涛.隧道内接触网基础槽型滑道预埋实践[J].电 气化铁道(增刊):78 -80.
Lv Jitao. Slide Channel Embedded Practice for Catenary foundation in Tunnel [ J ] . Electrified Railway:(S)78- 80.