研究结论:通过对接触网槽道施工工艺及控制措施分析,施工过程中可采用二次定位法来控制其施工精度和误差,即先确定槽道型号、间距、尺寸,在洞外采用固定模具或带刻度钢板上进行焊连成槽道组,然后再将槽道组放置在二衬模板台车对应的槽道预留孔位上,采用特制 T 型螺栓进行固定,混凝土浇筑完成后在拆模前再将 T 型螺栓卸除。
Abstract:Research purposes:The relative measures should be taken in building the precast channel for the catenary to make sure the errors of the embedding construction,incline construction and parallel construction do not exceed the limitation for meeting the requirements of the smooth transition and operational safety of the post - station four electrical interface.The study was done on the construction control technology for precast channel for catenary in tunnel to make sure all errors meet the requirement for providing the reference to the similar works.
Research conclusions:From the analysis of the construction technique and control measure for the channel for catenary in tunnel,it can be seen the construction precision and error can be controlled by using the secondary positioning technique. It means to confirm the type,gap and size of the precast channel and weld the precast channel into one unit with the fixed mould or the steel plate with scale outside of tunnel fiest. Then fix the precast channel unit on the hole position of the channel corresponding to the mould bogie for the secondary lining with special " T" type bolt,and the "T" type bolt will be removed before removing the mould.
张伯阳;严少发;任浩. 高速铁路隧道接触网预埋槽道施工控制技术[J]. 铁道工程学报, 2012, 29(9): 75-79.
ZHANG Bo - yang,YAN Shao - fa,REN Hao. Construction Control Technology for Precast Channel for Catenary in Tunnel of High - speed Railway. 铁道工程学报, 2012, 29(9): 75-79.
Guo Jiangang. Talking about the Construction Techniques for the Integrated Electrical Interface on Passenger Dedicated Line of Wuhan - Guangzhou Railway[J]. Sci - Tech Information Development & Economy,2009(15) : 198-201.
Meng Leping,Cao Yucheng. Passenger Special Railway Communication and Signal Interface Management[J]. Railway Signalling & Communication,2007 (5) : 34-37.
Han Ensuo,Wang Mingquan. Discussion on the Engineering Design,Construction Coordination and Management of the Interfaces Project Between Signal, Communication, Traction and Power Supply in Shijiazhuang - Taiyuan Railway[J]. Railway Signalling& Communication Engineering,2009(6) : 36-39.
Zhu Haibin. Construction Management and Control Technologies of Reserved Interface behind Station in Passenger Dedicated Lines[J]. Railway Construction Technology,2011(1) : 50-55.
Cai Xiyang. Application of " Four Electric" Integration to Building the Dedicated Line for Passengers [J]. Journal of Lanzhou Jiaotong University,2009(3) : 127-129.