Abstract Zhoujiacun extra-major bridge was constructed nearby existing Zhe-Gan railway line with Vo.26 & No.27 bridge piers across the No.Ⅱ line of Zhe-Gan Railway. Combined with the geologic conditions of that district and based on calculations of the loaded pressures, the methods for constructing bored concreting piles nearby existing railway line arc proposed. It is useful as reference for the similar engineering projects.
|