Program Research on Integrated Grounding System for Passenger Dedicated Railway Line |
YANG Gang |
The Second Survey and Design Institute of China Railway, Chengdu, Sichuan 610031, China |
|
|
Abstract Research purposes: This paper presents general requirement scope and specification of run-through ground wire, etc. of integrated grounding system. It has a significant meaning to satisfy construction demand of basic works in the civil engineering for passenger dedicated railway line at present.
Research methods: Integrated grounding system for passenger dedicated line is a complicatedly systematical project. Through making analysis of system's necessity and feasibility and program research, various groundings will be combined together properly to guarantee equipotential connection between various systems and between various, and reduce the potential differences between different equipment and between different systems and the hidden safety trouble for person and equipment due to potential difference.
Research conclusions: In order to guarantee operation safety and reliability of the complete system for passenger dedicated railway line, it is feasible to adopt integrated grounding system.
|
Received: 13 June 2006
|
|
|
|
|
[1] |
KieBling, Puschmann, Schmieder.电气化铁路接触网[M].北京:中国电力出版社,2004.
|
[3] |
铁道第二勘察设计院.遂渝线无碴轨道试验段信号阶段试验报告[Z].成都:铁道第二勘察设计院,2006.
|
[4] |
铁道部赴德国轨道电路一次参数测试组德国(博格、雷达2000)无碴轨道系统轨道电路一次参数测试报告[Z].铁道部赴德国轨道电路一次参数测试组,2005.
|
[2] |
铁道部工管[2006]18号文.关于印发《客运专线综合接地系统设计原则》(暂行)的通知[Z].2006.
|
|
|
|