Analysis and Discussion on Stress on End of Inserted Node Bar of Web Member of Steel Truss Girder |
Ai Zong—Hang,YUAN Ming,DAI Sheng—yong,HU Bu—mao,TONG Deng—guo,YANG Shan—kui |
China Railway Eryuan Engineering Group Co.Ltd,Chengdu,Sichuan 6 1003 1,China |
|
|
Abstract Research purposes: To facilitate the manufacture and installation,the integrated node is often adopted to the large—span continuous steel truss girder bridges.The web member is connected with the node of the main truss commonly by using high—strength bolts on two friction sides.As only two sides are connected,the other sides do not directly bear the load transferred from the gusset plate,and the shear lag effect appears.In order to analyze the shear lag effect and master plate stress distribution pattern on the end of web member and guide the design,the finite element models for 80me typical cross—-sections are establish to study the stress distribution on the end of the two—sides—connected web member.
Research conclusions:The maximum normal stress on the end of truss often occurs on the end of high—strength bolts.Generally speaking,the thicker the web member is and the more the row connected by bolt along the length direction of web member is,the small the ratio between maximum normal stress and nominal normal stress is.The changes of cross—section forms and thickness will not change the area of maximum shear stresses.At middle part of web member,the normal stress goes to uniform and the shear lag effect is not obvious.
|
Received: 30 October 2010
|
|
|
|
|
[1] 张建民,高锋.钢桁梁桥整体节点的优化分析[J].中国铁道科学,2001(5):89—92.
Zhang Jianmin,Gao Feng.Optimum Analysis of Steel Truss Integral Joints[J].China Railway Science,2001(5):89—92.
[2]陈毅明,谭永高,吴游宇.四渡河大桥钢桁梁节点板局部应力分析[J].桥梁建设,2008(1):58—61.
Chen Yiming,Tan Yonggao,Wu Youyu.Local Stress Analysis of Gusset Plates of Steel Truss Girder of Sidu River Bridge[J],Bridge Comtruction,2008(1):58—61.
[3]方志.上海闵浦二桥钢桁梁节点的应力分析[J].交通科技,2009(4):4—6.
Fang Zhi Stress Analysis of Steel Trussed Girder Nodes of Shanghai Minpu 2nd Bridge[J].Transportation Science&Technology,2009(4):4-6.
[4] 肖海珠,易伦雄.南京大胜关长江大桥主桥上部结构设计[J].桥梁建设,2010(1):1—4.
Xiao Haizhu.Yi Lunxiong.Design of Superstructure of Main
Bridge of Nanjing Dashengguan Changjiang River Bridge[J].Bridge Construction。2010(I):l一4.
[5]李仲襄,李军平,陶祖纪.厚板焊接整体节点制造技术[J]铁道工程学报,2002(1):102—106.
Li Zhongxiang,Li Junpin,Tao Zuji.Manufacturing Technique of Integrated Panel Point for Welding Thick Plate[J].Journal of Railway Engineering Society,2002(1):102—106.
[6]李厚祥,熊健民,余天庆,等.钢桁梁整体节点技术研究[J].湖北工学院学报,2001(1):44—47.
Li Houxlang,Xiong Jianmin,Yu Tianqing,etc.Test Study of Integral Panel Points of Steel Truss Girder [J].Journal of Hubei Polytechnic University,2001(1):44—47.
[7]赵廷衡,林荫岳.京九线孙口黄河大桥整体节点钢桁梁[J].铁道工程学报,1996(3):33—36.
Zhao Tingheng.Lin Yinyue.Steel Truss wim Solid Joints Used on Sunkou Huanghe Great Bridge in Jing—Jiu Railway Line[J].Journal of Railway Engineering Society,1996(3):33—36.
[8] 童登国,艾宗臣连续钢桁梁桥节点刚度对结构受力的影响研究[J].铁道建筑,2009(9):1—3.
Tong zhengguo,Ai Zongliang.Study about Effect of Nodal Stiffness of Continuous Steel Truss Girder Bridge on Internal Forces in Structure[J]. Railway Engineering,2009(9):1-3.
|
|
|
|