Design and Research on the Fuzhou-Xiamen Railway Bridge |
CHEN Lie |
China Railway Eryuan Engineering Group Co. Ltd, Chengdu, Sichuan 610031, China |
|
|
Abstract Research purposes: To have a study of such, key technology as the design principle for bridge on Fuzhou-Xiamen railway with a speed of 250 km/h, design on steel-box tied arch bridge with a span of 128 m, prestressed concrete continuous beam with spans of (80+3*144+80) m, and construction organization of simple supported box girder bridge over hill and dale section.
Research Conclusions: In principle the integral span simply supported box girder, prefabrication in girder yard, integral span transportation, bridge position erecting shall be adopted on the whole line, if impossible. It is necessary to perform some special treatment; the steel-box tied arch bridge with a span of 128 m and a rise-span ratio of 1/5.333 is mainly composed of steel box section and steel deck structure. After installed on the bracket, it will be positioned by dragging method. It is shown from static and dynamic analysis as well as fatigue test that such structure design is safe and reasonable; that the structural type of prestressed concrete continuous beam with spans of (80+3*144+80) m is reasonable for navigation; the continuous beam structure, bearing support for earthquake-isolation and reduction, and beam-fixed equipment are adopted for insuring the safety and rationality of the structural design; the measures for the partial flange plate off integral span box girder to be transported by way of tunnel, casting-in situ integral span box girder by overhead launching gantry are effective on settling the issues of integral span box girder transporting and erecting in the dense bridge-tunnel connection section.
|
Received: 28 October 2007
|
|
|
|
|
[1]中铁二院工程集团有限责任公司,铁道科学研究院.福厦铁路桥梁设计关键技术研究[R]. 2007.
[2]郭建勋,袁明,陈列,等.福厦铁路128 m钢系杆拱桥设计[J].铁道勘察,2007(增刊):34-37.
[3]铁建设[2005]140号.新建时速200~250公里客运专线铁路设计暂行规定(上、下)[S].
|
|
|
|