PRELIMINARY TALKING ABOUT GEOLOGIC ADVANCE FORECAST ON F5 FAULT IN CHANGLIANGSHAN TUNNEL |
BAI Heng-heng,XIN Min-gao |
Third Survey and Design Institute of MOR,Tianjin 300142 |
|
|
Abstract The Changliangshan Tunnel is a double-lined tunnel whose length is in the second order in China. Its geologic conditions are very complex with high difficulty in construction works- The F5 Fault is one of the biggest faults in this tunnel. The paper introduces the geologic advance forecast works on the F5 Fault by using synthetic methods, providing scientific base for its construction,and better effects are also obtained.
|
Received: 18 November 1999
|
|
|
|
|
[1]隧道施工开挖工作面前方不良地质预报[R].地质物探试 验研究中心,1995- 04.
[2]隧道施工掌子面前方不良地质地震反射法超前预报研究 试验阶段报告[R].铁道部第一勘测设计院,1990- 12.
[3]弹性波反射法在隧道施工超前预报中的应用[R].铁道部 第一勘测设计院,1997- 10. |
|
|
|