铁路特长单线隧道钻爆施工机械配置探讨

刘元重,方俊波

铁道工程学报 ›› 2003, Vol. 20 ›› Issue (1) : 129-132.

PDF(165 KB)
PDF(165 KB)
铁道工程学报 ›› 2003, Vol. 20 ›› Issue (1) : 129-132.
路网研究

铁路特长单线隧道钻爆施工机械配置探讨

  • 刘元重1,方俊波2
作者信息 +

EXPLORATION ON ALLOCATION OF CONSTRUCTION MACHINERY FOR DRILLING AND BLASTING OPERATION OF RAILWAY EXTRA-LONG SINGLE-TRACKED TUNNELS

  • LIU Yuan-zhong1, FANG Jun-bo2
Author information +
文章历史 +

摘要

本文介绍了在建渝怀铁路最长单线隧道-圆梁山隧道的施工机械配置情况,阐明了采用常规施工方法(全断面法或下导坑法)及配置国产设备亦能实现铁路特长单线隧道掘进速度的稳产和高产,论述了施工机械设备的良好配置是确保特长隧道快速掘进的关键所在,同时对今后我国特长单线隧道的机械配置提出几点建议。

Abstract

Yuanliangshan Tunnel is the longest single-tracked tunnel during construction of Yu-Huai Railway. The allocation of its construction machinery is introduced in this paper. It is expounded that by adopting the traditional construction methods (such as full face tunnelling method or lower guide-adit method) and allocating national-made machinery may obtain also stable and high-efficient rapid tunnelling speed for construction of railway extra-long single-tracked tunnels. Therefore, the good allocation of construction machinery is the key for guarantee rapid tunnelling of extra-long tunnels. At the same time, several suggestions are proposed for allocation of construction machinery for extra-long single-tracked tunnels in China in the future.

关键词

特长单线隧道 / 快速掘进 / 无轨装碴 / 有轨运输

Key words

extra-long single-tracked tunnel / rapid tunnelling / non-rail disposal of spoil / spoil conveying out through rail

引用本文

导出引用
刘元重, 方俊波. 铁路特长单线隧道钻爆施工机械配置探讨[J]. 铁道工程学报, 2003, 20(1): 129-132
LIU Yuan-zhong, FANG Jun-bo. EXPLORATION ON ALLOCATION OF CONSTRUCTION MACHINERY FOR DRILLING AND BLASTING OPERATION OF RAILWAY EXTRA-LONG SINGLE-TRACKED TUNNELS[J]. Journal of Railway Engineering Society, 2003, 20(1): 129-132
中图分类号: U455.32   

参考文献

[1]林志清,等.达万铁路山湾隧道均衡施工技术[A].见:第10届隧道和地下工程科技动态报告文集[C]. 成都:西南交通大学出版社,2000-06.
[2]刘元重.寺铺尖隧道施工技术浅谈[J].隧道建设,1997,(3).
[3]曹红彬.大竹林隧道进口端快速施工技术[J].西部探矿工程,2000,(4).