黔桂线扩能改造工程主要技术标准研究

黄 波

铁道工程学报 ›› 2010, Vol. 27 ›› Issue (8) : 1-6.

PDF(541 KB)
PDF(541 KB)
铁道工程学报 ›› 2010, Vol. 27 ›› Issue (8) : 1-6.
路网研究

黔桂线扩能改造工程主要技术标准研究

  • 黄 波
作者信息 +

Research on Main Technical Standards for Upgrading of Guizhou—Guangxi Railway

  • HUANG Bo
Author information +
文章历史 +

摘要

研究目的:本文介绍黔桂铁路(贵阳一柳州)的线路走向和工程概况。其中重点介绍扩能改造措施及主要技术标准研究,扩能方案的比选、限制坡度、以及提速改造,速度目标值、正线数目的比选,工程实施效果等,以期对电气化铁路的扩能改造提供借鉴。
研究结论:电气化I级铁路、单线预留复线,柳州一洛满段增建二线。限制坡度:6‰,双机13‰,牵引质量3 800 t。柳州至金城江段按160 km/h速度目标值设计,金城江至龙里段按140 km/h速度目标值设计,并酌留余量。

Abstract

Research purposes: This paper introduces the alignment and the general upgrading of Guizhou—Guangxi Railway(Guiyang—Liuzhou),including the upgrading measures,research on main technical standards,the comparison and selection of upgrading schemes,ruling gradient,speed target value and number of main track,as well as upgrading effect,for the purpose of providing the reference to the upgrading of electrified railway.
Research conclusions: The Guizhou—Guangxi Railway is upgraded as Grade I electrified railway with singkle track, reversing condition for double tracks.The additional second track from Liuzhou to Luoman will be built.The ruling gradient is 6‰ and the ruling gradient is 1 3‰ in the section with double locomotive traction.The driving load is 3 800 t.The 160 km/h speed target value is desined for the Liuzhou—Jinchengjiang section and 140 km/h speed target value is designed for the Jinehengjiang—Longli section with some design margin.

关键词

黔桂铁路 / 扩能改造措施 / 技术标准 / 速度目标值比选

Key words

Guizhou—Guangxi Railway / upgrading measure / technical standards / comparison and selection of speed target value

引用本文

导出引用
黄 波. 黔桂线扩能改造工程主要技术标准研究[J]. 铁道工程学报, 2010, 27(8): 1-6
HUANG Bo. Research on Main Technical Standards for Upgrading of Guizhou—Guangxi Railway[J]. Journal of Railway Engineering Society, 2010, 27(8): 1-6
中图分类号: U212.31   

参考文献

[1] 铁鉴函[2004]655号文,关于5黔桂线扩能改造初步设计 审查批复意见6[S].
Tie Jian Han [2004] No. 655, About Reply Opinion to the Preliminary Design Review on Reconstruction of Guizhou -Guangxi Railway [S].
[2] 张雪才,等.改建铁路黔桂线预可行性研究[R].成都: 铁道部第二勘测设计院, 2001.
Zhang Xuecai, eta.l Pre - feasibility Study on Reconstruction of Guizhou -Guangxi Railway [R ]. Chengdu: The Second Survey and Design Institute of China Railways, 2001.
[3] 王南,等.改建铁路黔桂线可行性研究[R].成都:铁道 第二勘察设计院, 2003.
Wang Nan, eta.l Feasibility Study on Reconstructed Guizhou -Guangxi Railway[R ]. Chengdu: The Second Survey and Design Institute of China Railways, 2003.
[4] 林世金,邓军桥,等.改建铁路黔桂线初步设计[Z ].成 都:铁道第二勘察设计院, 2004.
Lin Shijin, Deng Junqiao, eta.l Preliminary Design of Reconstruction of Guizhou -Guangxi Railway [Z ]. Chengdu: The Second Survey and Design Institute of China Railways, 2004.
[5] 王毅,黄波,等.改建铁路黔桂线施工图[Z ].成都:铁道 第二勘察设计院, 2006.
Wang Yi, Huang Bo, eta.l Construction Drawing of Reconstructed Guizhou - Guangxi Railway [ Z ]. Chengdu: The Second Survey and Design Institute of China Railways, 2006.
[6] 铁道部第一勘测设计院.铁路工程设计技术手册线路 [K]. 2版.北京:中国铁道出版社, 1994.
China Railway First Survey and Design Institute Group Ltd. Technical Manual for Design of Railway Engineering -Route (Revised Edition) [K ]. Beijing: China Railway Publishing House, 1994.
[7] 朱颖.铁路选线理念的创新与实践[J].铁道工程学报, 2009(6): 1 -5.
Zhu Ying. Innovation and Practice on Railway Location Concept [J]. Journal of Railway Engineering Society, 2009 (6): 1 -5.
[8] 赵月霞.铁路建设与城市环境[J].铁道经济研究, 2005 (4): 44 -46.
Zhao Yuexia. Railway Construction and City Railway Construction and City Environment [ J ]. Railway Economics Research, 2005 (4): 44 -46.
[9] 刘高琥,黄军.武广高速铁路韶关至花都段工程设计实践 及特点[J].高速铁路技术, 2010(1): 36 -39.
Liu Gaofu,Huang Jun. Design Practice and Feature of Shaoguan-Huadu Section of Wu-Guang Passenger Dedicated Railway Project [J ]. High Speed Railway Technology, 2010 (1): 36 -39.
[10]杜宇本,蒋良文.大瑞铁路大保段主要工程地质问题及地 质选线[J].铁道工程学报, 2010(4): 23 -27.
Du Yuben, Jiang Liangwen. Main Problems in Engineering Geology and Alignment in Dali -Baoshan Section of Dali-Ruili Railway [J]. Journal of Railway Engineering Society, 2010 (4): 23 -27.
 

PDF(541 KB)

2964

Accesses

0

Citation

Detail

段落导航
相关文章

/