研究目的:为了研究渤海海峡海底特长隧道施工控制测量对施工贯通的影响,针对设计方案中最长贯通距离的海底特长隧道进行贯通误差估算分析,并根据贯通误差对施工控制网精度进行设计。研究结论:(1)影响隧道贯通误差有洞外GPS控制测量、洞内导线测量、洞外跨海高程传递和洞内水准测量四个方面,其中洞内导线控制测量和洞外跨海高程传递测量精度对贯通误差影响更为显著;(2)提出了渤海海峡海底最长开挖长度贯通面间的贯通误差限差和洞内外平面、高程控制网精度建议方案;(3)就目前的测量手段、方法和测量精度,对于渤海海峡海底特长隧道的开挖贯通在测量技术上是可行的,贯通误差是可控的;(4)研究成果对渤海海峡铁路通道海底隧道及类似工程施工控制测量的技术方案制定及实施具有参考价值。
Abstract
In order to study the influence of the undersea tunnel of Bohai Strait construction control survey on construction completed, the breakthrough error is estimated and analyzed based on the designed undersea tunnel with the longest length. According to the breakthrough error, the precision of construction control network is designed. Research conclusions:(1)The breakthrough error of tunnel affected from four aspects, such as outside tunnel GPS control survey, inside tunnel traversing, outside height transfer across the strait and inside tunnel leveling. The inside tunnel traversing and outside height transfer across the strait have more significant impact on breakthrough error. (2)This paper has proposed some suggestions about the tolerance of breakthrough error of the Bohai Strait tunnel between the longest breakthrough faces, and the solution on precision design of horizontal and vertical control network of inside and outside tunnel. (3)By the current measuring tools, methods and accuracy, the surveying technology for the construction and the breakthrough of Bohai Strait undersea long tunnel is feasible, and its breakthrough error is controllable. (4)The research results have important reference value for the technical plan making and its implementation of construction control survey for undersea tunnel of Bohai Strait railway corridor and similar project.
关键词
铁路工程测量 /
控制测量 /
隧道 /
贯通误差 /
精度设计
{{custom_keyword}} /
Key words
railway engineering survey /
control survey /
tunnel /
breakthrough error /
precision design
{{custom_keyword}} /
中图分类号:
P258
{{custom_clc.code}}
({{custom_clc.text}})
{{custom_sec.title}}
{{custom_sec.title}}
{{custom_sec.content}}
参考文献
[1] 卢光杰,田宝红.渤海海峡跨海通道建设方案研究[J].铁道标准设计,2013(8):37-41.
Lu Guangjie, Tian Baohong. Research on Development Scheme of Sea-crossing Railway through the Bohai Channel[J]. Railway Standard Design,2013(8):37-41.
[2] 姚连璧,李文全.隧道GPS网横向贯通误差的计算[J].铁道工程学报,1995(4):80-85.
Yao Lianbi, Li Wenquan. The Calculation of Tunnel GPS Network on the Precision of the Lateral Link-up[J]. Journal of Railway Engineering Society,1995(4):80-85.
[3] TB 10601—2009,高速铁路工程测量规范[S].
TB 10101—2009,Code for Engineering Survey of High-speed Railway[S].
[4] GB/T 12897—2006,国家一、二等水准测量规范[S].
GB/T 12897—2006,Specifications for the First and Second Order Leveling[S].
[5] GB/T 18314—2009,全球定位系统(GPS)测量规范[S].
GB/T 18314—2009,Specifications for Global Positioning System(GPS) Surveys[S].
[6] 孔祥元,梅是义.控制测量学[M].武汉:武汉大学出版社,2002.
Kong Xiangyuan, Mei Shiyi . Control Surveying[M] . Wuhan:Wuhan University Press, 2002.
[7] 武汉大学测绘学院测量平差学科组.误差理论与测量平差基础[M].武汉:武汉大学出版社,2003.
Scholl of Geodesy and Geomatics, Wuhan University . Error Theory and Foundation of Surveying Adjustment[M]. Wuhan:Wuhan University Press, 2003.
[8] 张项铎,张正禄.隧道工程测量 [M].北京:测绘出版社,1998.
Zhang Xiangduo,Zhang Zhenglu. Tunnel Engineering Survey[M] . Beijing:Surveying and Mapping Press, 1998.
{{custom_fnGroup.title_cn}}
脚注
{{custom_fn.content}}
基金
铁道第三勘察设计院集团有限公司2014年重点科研课题《渤海海峡铁路通道控制测量前期研究》
{{custom_fund}}