不均匀沉降对大跨连续梁及轨道结构影响分析

邹振华

铁道工程学报 ›› 2014, Vol. 31 ›› Issue (3) : 61-65.

PDF(1343 KB)
PDF(1343 KB)
铁道工程学报 ›› 2014, Vol. 31 ›› Issue (3) : 61-65.
桥梁工程

不均匀沉降对大跨连续梁及轨道结构影响分析

  • 邹振华
作者信息 +

Effects Analysis of Differential Settlementon on Long-span Continuous Bridge and Ballastless Track Structure

  • ZOU Zhen-hua
Author information +
文章历史 +

摘要

研究目的:本文结合某高速铁路大跨度无砟轨道桥梁不均匀沉降工程实例,分析墩台发生不均匀沉降工况下,桥梁结构及桥上无砟轨道受力情况,并对结构安全性和适应性进行综合分析,最后根据沉降值范围,提出相应的处理方案及建议。论文旨在通过针对性研究,对今后大跨连续梁不均匀沉降的整治处理提供参考。
研究结论:通过计算分析得出:(1)大跨连续梁不均匀沉降值超过现行设计规范一定范围时,对墩台受力影响较小,对连续梁主梁及轨道受力影响可控;(2)现行规范应适当放宽对大跨连续梁不均匀沉降的限值,有利于在设计阶段从源头上既保证结构安全又节约建设成本;(3)对较大的不均匀沉降应及时采取措施进行综合整治;(4)该研究成果可应用于铁路大跨连续梁因软土地基、地下水位变化等因素引起的墩台不均匀沉降整治。

Abstract

Research purposes:This paper,associated with a certain engineering project of differential settlement on ballastless track long-span bridge in high-speed railway,analyzes the bridge structure and ballastless track stress on bridge under operation condition with diverse differential settlement value.Through comprehensive analysis of structure safety and adaptability,the relevant solutions and suggestions are proposed.Through targeted research,this paper is aimed at providing the reference for remediation processing of large-span continuous beam differential settlement in the future. Research conclusions:When long-span continuous beam differential settlement value is more than a certain range of the current design code,the stress influence on the pier is less,the effect on continuous beam girder and rail is controllable.The current code limit value for long-span continuous beam differential settlement should be appropriate to relax,to guarantee the safety of the structure and save the construction cost.At the same time,the larger differential settlement should be taken timely measures to carry out comprehensive improvement.The research results can be applied to differential settlement remediation of the railway long-span continuous beam pier caused by soft soil,groundwater level changes and other factors.

关键词

桥梁 / 墩台 / 不均匀沉降 / 结构分析

Key words

bridge pier / differential settlement / structure analysis

引用本文

导出引用
邹振华. 不均匀沉降对大跨连续梁及轨道结构影响分析[J]. 铁道工程学报, 2014, 31(3): 61-65
ZOU Zhen-hua. Effects Analysis of Differential Settlementon on Long-span Continuous Bridge and Ballastless Track Structure[J]. Journal of Railway Engineering Society, 2014, 31(3): 61-65
中图分类号: U215.8   

参考文献

[1]TB 10621—2009,高速铁路设计规范(试行)[s].
TB 10621—2009,Code for Design of High Speed Railway[S].
[2]TB 10002.3—2005,铁路桥涵钢筋混凝土和预应力混凝土结构设计规范[S].
TB 10002.3—200S.Code for Design on Reinforced and Prestressed Concrete Structure of Railway Bridge and Culvert[S].
[3]江忠贵.高速铁路与客运专线施工工艺手册[M].北京:中国铁道出版社,2006.
Jiang Zhonggui.High Speed Railway and Passenger Dedicated Line Construction Technology of Manual[M].Beijing:China Railway Publishing House,2006.
[4] 孙宗磊.石济客专桥梁下穿京沪高铁沉降影响分析[J].铁道工程学报,2013(2):53-55.
Sun Zonglei.Analysis of Settlement Influence on Beijing-Shanghai High-speed Railway Caused by Under-passing of Shijiazhuang-Jinan Passenger Dedicated Line 7S Bridge[J].Journal of Railway Engineering Society。2013(2):53-57.