Abstract:Research purposes:There have been difficulties in signal design of CTCS-3 to CTCS-2 level transition between the stations in complex hub,it is necessary to analyze the principles,summarize the practical engineering cases,and extract the user-friendly design methods for future similar scenarios to provide reference for engineering design.
Research conclusions:(1)The fundamental conditions of CTCS-3 to CTCS-2 level transition is:the distance from YG-3/2 balise group to the CZ balise group should be greater than 450 m,the distance from the YG-3/2 balise group to ZX-3/2 balise group should be greater than Ss traveled distance at maximum allowable line speed,the scope of the RBC data configuration should extend at least one braking distance from the execution point.(2)When two CTCS-3 yards in a row integrate and belong to two different RBC,the CTCS-3 to CTCS-2 level transition can be carried out on the cross-field line between the two yard,the CTCS-3 to CTCS-2 level transition can be carried out after running across the cross-field lines,then it achieves the RBC handover.(3)When two CTCS-3 and CTCS-2 yards in a row integrate and have more than two cross-field lines,CTCS-3 to CTCS-2 level transition can be carried on two cross- field lines. (4)When the length of the cross-field line between CTCS-3 yard to CTCS-2 yard does not meet the basic conditions of level transition,the CTCS-3 to CTCS-2 level transition point can be set on the CTCS-2 line. (5)The research conclusions can provide a reference for the signal design of train control system when there exists cross -filed line.
项守宽. 特殊跨线场景下的CTCS - 3至CTCS – 2列控等级转换方法[J]. 铁道工程学报, 2015, 32(8): 91-95.
XIANG Shou-kuan. CTCS-3 to CTCS-2 Train Control System Level Transition Method in Specific Scenarios of Crossing the Line. Journal of Railway Engineering Society, 2015, 32(8): 91-95.
Science and Technology Transport[2010]No. 21,The Balise Application Principles of CTCS-3 Train Control System ( V2. 0 )[S].
[1]
科技运[2010]21号,CTCS-3级列控系统应答器应用原 则(V2.0)[S]
Basic Science Department of Railway Transportation Bureau-Signal [ 2011]No. 170,CTCS-2/CTCS-3 Train Control System Level Transition Application Principles(V1.0)[S].
China Railway Siyuan Survey and Design Group Co. Ltd. Jinhua-Wenzhou Railway Expansion Renovation Project Construction Design[R].Wuhan:China Railway Siyuan Survey and Design Group Co. Ltd. 2014.
[2]
科技运[2010]136号,CTCS-2级列控系统应答器应用 原则(V2.0) [S]
Gao Ye. CTCS-3 to CTCS-2 Level Transition Balise Group Arrangement[J].Railway Signaling& Communication Engineering , 2014 ( 5) ; 29-31.
Xiang Shoukuan. Train Control Balise Arrangement and Engineering Data Process Scheme in Several Special Scenarios[J].Railway Signal&Communication Engineering and Technology , 2012 ( 3) ; 5-7.
China Railway Siyuan Survey and Design Group Co. Ltd. Hangzhou-Changsha Passenger Dedicated Line Construction Design[R].W uhan:China Railway Siyuan Survey and Design Group Co. Ltd, 2013.
Science and Technology Transport[2010]No. 136,The Balise Application Principles of CTCS-2 Train Control System( V2.0)[S].