Abstract:Research purposes: Based on the on - site investigation,the tests were done to the road base of the existingBaicheng - Aershan Railway with the dynamic penetration test,K30 test,Evd test and spectral analysis of surface waves,and the comprehensive evaluation was carried out to the existing road base by analyzing and studying the test data to prove whether the road base can continue to maintain the good condition or not after the speed - raise for the purpose of providing the technical basis for the design and scheme comparison of the speed - raise project.
Research conclusions: Based on the on - site investigation and the composition of subgrade filling of the existing railway,it is necessary to evaluate the subgrade of the existing railway section by section to reduces the negative influence caused by discrete data and improve the accuracy of the valuation results. The defect locations of existing Baicheng - Aershan Railway in bearing capacity and strength mainly concentrate in the range of 0. 0 ~ 0. 6 m of the road base's surface and 0. 6 ~ 1. 2 m range of the bottom. The deep filling should be conducted to them in a big range for more test and evaluation. The dynamic penetration test has features of simple operation and wide applicability,but itstest data is of big discreteness and how to reduce the error is the problem to be resolved in future. Compared with the Evd ,the K30 requires a lot of human and material resources and much time . The comparative experiment can be done to the existing railways of different grade with these two methods to explores the relation between Evd and K30,and substituting Evd for K30 partially in the test points can improve the work efficiency. The defect position and scope of railway road base in the bearing capacity and strength can be accurately revealled by using the spectral analysis of surface waves along with the dynamic penetration test to evaluate the condition of the existing road base.
赵凤林,张健. 既有线铁路路基基床评价与测试研究[J]. 铁道工程学报, 2011, 28(4): 15-21.
ZHAO Feng - lin,ZHANG Jian. Study on Evaluation and Test of Road Base of Existing Railway. 铁道工程学报, 2011, 28(4): 15-21.
China Railway Construction Letter [2005] N0. 285,The Temporary Regulations for the Designs of the Newly Built Passenger and Freight Railway with the Speed of 200 km/h [S].
Zhao Wen,Xie Qiang,Yongping Chen. Experimental Research on the Proposed Standard for Subgrade Compaction Quality with Evd Evaluation [J]. Journal of Railway Engineering Society,2009( 9) : 9 - 13.
Yang Xin’an,Gao Yanling,Liu Zheng. Inspection on Railway Track Substructure [J]. Chinese Journal of Rock Mechanics and Engineering,2003 ( S1 ) : 2363 -2366.