Abstract:Research purposes: The purposes were to sum up the treatment of disease of high side slope in section of K 207+939~K 208+200 of SA8 Contract for Sanming-Fuzhou Highway.
Research methods: Based on several experiments, the relevant construction parameters were obtained and suitable construction method was found out through practices of organization and management, in combination with changeable situations on site.
Research conclusions: The first stair had to have enough width and the operation of all links to constructional tension had to be normalized when constructing on high side slope. In this way, the good result could be obtained.