Abstract:Research purposes: To determine the speed targetvalue ofnew railway line formixed passenger and freight traffic should not only consider the demand of speed target value, but also should consider the influence of time difference caused by the feature of the line. The limit slope standard much affects the line trend, line length,construction investmen,t operating costs, traction quality and traffic capacity.
Research conclusions:The speed targetvalue of200 km /h used for this railway line canwellmeet the requirementsof the time targetvalue and coordinatewith the speed targetvaluesofJinan-QingdaoPassengerDedicated Line, Qingdao-Rongcheng Intercity Line, Lianyungang -Yancheng Line. The limit6jslope on this line can meet the demand of traffic capacity of this line andwellmatch the adjacent railway line in network.
左 峰. 青连铁路速度目标值和限制坡度标准选择分析[J]. 铁道工程学报, 2009, 26(12): 30-34.
ZUO Feng. Analysis of Selection of Target Speed Value and Lmi it Slope Standard of Q ingdao-Lianyungang Railway. 铁道工程学报, 2009, 26(12): 30-34.