Abstract:Research purposes:The newly-built Liangfengya Tunnel of Chongqing-Guizhou Railway is the control engineering,which is located at the joint and compound part of the north-south and north-east meridional tectonic belt,and goes through the Liangfengya (the Qishierdaoguai,210 National Rd.)of Loushan Mountain. In the tunnel area, the karst spreads widely,and the karst beneath channelizes,commonly spring points and underground rivers scatter, the conditions for geological structure and karst hydrogeology are complicated,so that it is necessary to verify the karst hydrogeologic conditions for the tunnel.
Research conclusions : Through the systematic research on the lithological association characteristics of aquifer stratum, hydrodynamic field of karstic water, hydrochemical field and karstic water, this article reached the following conclusion: (1)Karstic water at the tunnel location can be divided into two first level units and seven secondary units.(2)The normal water inflow prediction for the tunnel shall be expressed by Q=24 542 m3/d,and the large water inflow in the rainy season shall be expressed by QL=73626m3/d. (3)The karst water gushing risk in general is medium-high in the carbonate rock section of tunnel.(4)As to the deeply buried carbonate rock of tunnel north,the development degree of the karst and the enrichment degree for underground water are poorer, while in the south the development degree of the karst and the enrichment of the underground are higher, which affect the tunnel water inflow largely. (5)This article can be a directive and exemplificative case for the tunnel survey and design of railway and highway in carbonate rock regions.
徐正宣,冯建林,索朗. 渝黔铁路凉风垭隧道岩溶水文地质条件研究[J]. 铁道工程学报, 2014, 31(6): 56-61.
XU Zheng-xuan,FENG Jian-lin, SUO Lang. Karst Hydrogeology Research on the Liangfengya Tunnel of Chongqing- Guizhou Railway. Journal of Railway Engineering Society, 2014, 31(6): 56-61.
TB 10012一2007,Code for Geology Investigation of Railway Engineering [ S ]
[2] TB 10027—2012,铁路工程不良地质勘察规程[S].
TB 10027—2012,Code for Unfavorable Geological Condition Investigation of Railway Engineering [ S].
[3] TB 10049—2004,铁路工程水文地质勘察规程[S].
TB 10049一2004,Code for Hydrogeological Investigation of Railwaty Engineering [ S].
[4]冯建林,徐正宣,索朗,等.改建铁路重庆至贵阳线工程地质报告+ ,.中铁二院工程集团有限责任公司,2009. Feng Jianlin, Xu Zhengxuan,Suo Lang, etc. Engineering Geology Report on Reconstruction of Chongqing to Guiyang Route [ R ]. China Railway Eryuan Engineering Group Co. Ltd,2009.